Miscellaneous action | | | 4/8/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 11/29/2012 | 11/29/2012 | 11/29/2012 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Supply line flush | 10/2/2012 | 10/3/2012 | 10/3/2012 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2012 | 10/1/2012 | 10/1/2012 | P | NR |
Forrest France
|
|
|
No access to the UG gate valve to complete flushing operation.
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2012 | 9/10/2012 | 9/10/2012 | P | PASS |
Troy Cobbley
|
|
|
Underground supply hydro passed.
|
INSP-Sprinkler Rough-in | 8/23/2012 | 8/23/2012 | 8/23/2012 | P | PART |
Forrest France
|
|
|
UG fire supply line approved for cover including the additional 11 deg ell.
|
Plan assigned to (Tim) | 8/9/2012 | | 8/13/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/13/2012 | | 8/13/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/13/2012 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/13/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/13/2012 | | 8/13/2012 | | DONE |
Darla L Downs
|
|
|
|
Telephone call | | | 8/13/2012 | | |
|
|
|
8-13-12 called Brodie- Treasure Valley Fire permit ready and fee given ///dld
|
Permit Ready to Issue | | | 8/13/2012 | | |
|
|
|
|
Issue and Print Permit | | | 8/13/2012 | | DONE |
|
|
|
|
Application received | | | 8/9/2012 | | |
|
|
|
|
Case Summary | | | 8/9/2012 | | DONE |
|
|
|
|