Miscellaneous action | | | 9/24/2013 | | DONE |
|
|
|
Documents scanned into Onbase and Tidemark
|
INSP-Final Inspection | 4/8/2013 | 4/9/2013 | 4/9/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/8/2013 | 4/8/2013 | 4/8/2013 | P | FAIL |
Troy Cobbley
|
|
|
Unable to finish inspection due to the fire sprinkler contractor not being ready. All items tested ok except testing for the fire sprinkler devices. Rick is going to provide as-builts showing the additional duct smoke detector.
|
INSP-Conference | 3/22/2013 | 3/22/2013 | 3/22/2013 | P | DONE |
Troy Cobbley
|
|
|
Confernece was a request to relocate the remote annunciator to the east doors. I deferred the approval to Romeo in the fire dept
|
FIR-Aging Inspection | 2/19/2013 | 2/19/2013 | 2/19/2013 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
Issue and Print Permit | | | 9/19/2012 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 9/5/2012 | | 9/12/2012 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 9/12/2012 | | PASS |
|
|
|
|
Alarm Plan Check | 9/12/2012 | | 9/12/2012 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 9/12/2012 | | DONE |
|
|
|
Approved redlined plans taken to permit technician for processing.
|
Inspection Record Card- Fire | 9/12/2012 | | 9/12/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 9/12/2012 | | |
|
|
|
|
Telephone call | | | 9/12/2012 | | |
|
|
|
9-12-12 called left message with Rick permit ready and fee given ///dld
|
Application received | | | 9/5/2012 | | |
|
|
|
|