Miscellaneous action | | | 4/8/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 11/15/2012 | 11/15/2012 | 11/15/2012 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 11/12/2012 | 11/14/2012 | 11/14/2012 | A | FAIL |
Forrest France
|
|
|
Missing one additional head to be added per plan due to a new wall at the 9th floor corridor. See plans for marked location.
|
INSP-Sprinkler Rough-in | 10/31/2012 | 11/1/2012 | 11/1/2012 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. piping is ok to cover. Contractor needs to verify if the hangers need to meet NFPA 13 requirements for exceeding 100psi. Thiis applies to the modified heads. Also the pendant heads in the 9th floor conference room near the stairs are blocked by surface mount lights.
|
Issue and Print Permit | | | 9/20/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 9/12/2012 | | 9/19/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/19/2012 | | 9/19/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 9/19/2012 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 9/19/2012 | | 9/19/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 9/19/2012 | | |
|
|
|
|
Telephone call | | | 9/19/2012 | | |
|
|
|
9-19-12 called Shilo Automatic Sprinkler permit ready and fee given ///dld
|
Miscellaneous action | | | 9/14/2012 | | DONE |
|
|
|
Review on hold pending flow test information.
|
Application received | | | 9/12/2012 | | DONE |
Barbara Stitt
|
|
|
|