Miscellaneous action | | | 4/8/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Forrest France
|
|
|
Noted correction items completed, final walkthrough passed. Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 10/24/2012 | 10/25/2012 | 10/29/2012 | P | PART |
Forrest France
|
|
|
Overhead rough-in approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2012 | 10/26/2012 | 10/26/2012 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed acceptable including the FDC supply.
|
INSP-Sprinkler Rough-in | 10/24/2012 | 10/24/2012 | 10/24/2012 | P | FAIL |
Forrest France
|
|
|
Overspaced heads at two locations, four open outlets, one end of line at the second floor needs tenting adjusted. See stamped plan set for marked areas.
|
INSP-Sprinkler Rough-in | 10/22/2012 | 10/23/2012 | 10/23/2012 | A | FAIL |
Forrest France
|
|
|
Noted four pendent heads in need of relocation due to light fixture obstructions, heads at furnace closets to meet temp. ratings per 6.2.3.3.3, verify equipment at the exterior balcony rooms are not fuel-fired.
|
Plan assigned to (Tim) | 9/17/2012 | | 9/24/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/24/2012 | | 9/24/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 9/24/2012 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2012 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 9/24/2012 | | DONE |
Christina Prado
|
|
|
called Cameron to advise permit is ready and gave fees due
|
Inspection Record Card- Fire | 9/24/2012 | | 9/24/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 9/24/2012 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 9/24/2012 | | DONE |
|
|
|
|
Application received | | | 9/17/2012 | | |
|
|
|
|