Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 7/24/2013 | 7/25/2013 | 7/26/2013 | P | PASS |
Forrest France
|
|
|
|
INSP-Supply line flush | 7/8/2013 | 7/9/2013 | 7/9/2013 | A | PASS |
Troy Cobbley
|
|
|
Performed six underground flushes for the remaining buildings. All six passed.
|
INSP-Supply line flush | 5/9/2013 | 5/10/2013 | 5/10/2013 | A | PASS |
Troy Cobbley
|
|
|
The underground flush for the four north most units passed.
|
FIR-Aging Inspection | 4/25/2013 | 4/25/2013 | 4/25/2013 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|
INSP-Sprinkler Rough-in | 1/15/2013 | 1/15/2013 | 1/15/2013 | P | PASS |
Troy Cobbley
|
|
|
Tenting passed. Sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 1/9/2013 | 1/9/2013 | 1/9/2013 | P | PASS |
Troy Cobbley
|
|
|
Piping at address 2012 is ok to cover
|
INSP-Sprinkler Rough-in | 10/15/2012 | 10/16/2012 | 10/16/2012 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the multiple locations where the undergorund supply lines are ok to cover. Additional fittings have been added and will need to be reflected in the overhead hydraulic calculations.
|
Issue and Print Permit | | | 10/12/2012 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 10/11/2012 | | 10/11/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 10/11/2012 | | DONE |
Barbara Stitt
|
|
|
Called Brad and told him that permit is ready & fees due on 10-11-12 @ 8:30am//BAS
|
Permit Ready to Issue | | | 10/11/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 10/9/2012 | | 10/10/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/10/2012 | | 10/10/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 10/10/2012 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2012 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/9/2012 | | |
|
|
|
|