Miscellaneous action | | | 4/16/2013 | | DONE |
|
|
|
Plans taken to records for scanning
|
INSP-Final Inspection | 3/15/2013 | 3/15/2013 | 3/15/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 3/15/2013 | | DONE |
|
|
|
Recieved an email from Brian at Local Fire explaining the modifications made to the the fire alarm system. They included:
1.We removed fire hat relay for elevators because the elevators do not have fire hat option.
2.We added 2 smoke detectors to the elevator mechanical room due to concrete barriers.
3.We relocated the 1st floor stairwell pull stations from the hall to inside the stairwell by the stairwell exit doors.
4.We removed the fire pump phase reversal module because the pump equipment does not do phase reversal.
5.We added one 15 cd strobe on 4th floor in an exam room that showed as an office on the original plan.
6.We added 2 15 cd strobes on 5th floor. One in a conference room that showed as an office and one in a break room that showed as an office.
I let him know this was acceptable for as-builts and would not require a plan modification.
|
INSP-Final Inspection | 3/13/2013 | 3/14/2013 | 3/14/2013 | A | FAIL |
Troy Cobbley
|
|
|
Provide as-builts, provide e-mail verification to plan review of changes(include fireman's hat issue), provide signal verification, provide record of completion.
|
Alarm Plan Check | 12/31/2012 | | 12/31/2012 | | PASS |
Stephanie L. Cobbley
|
|
|
Resubmittals approved with redlines and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 12/31/2012 | | DONE |
|
|
|
Approved redlined resubmittals taken to permit technician for processing.
|
Permit Ready to Issue | | | 12/31/2012 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 12/31/2012 | | 12/31/2012 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 12/31/2012 | | DONE |
Barbara Stitt
|
|
|
Called Brian and told him that permit is ready & fees due on 12-31-12 @ 10:15am///BAS
|
Permit Ready to Issue | | | 12/31/2012 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/31/2012 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 10/11/2012 | | 12/31/2012 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan resubmittals received | | | 12/26/2012 | | |
|
|
|
received 2 applications & 2 sets of plans sent to SLC
|
1st review completed | | | 10/18/2012 | | FAIL |
|
|
|
|
Alarm Plan Check | 10/18/2012 | | 10/18/2012 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans denied with redlines and review comments.
|
Miscellaneous action | | | 10/18/2012 | | DONE |
|
|
|
Applicant did not provide a fax number, so I emailed him to let him know the plans have been denied and that he could pick up the redlines and review comments at the permit desk.
|
Miscellaneous action | | | 10/18/2012 | | DONE |
|
|
|
Plans taken to the permit counter and placed in the drawer.
|
Miscellaneous action | | | 10/17/2012 | | DONE |
|
|
|
Sent an email to Brian with Local Fire & Security requesting information. The plans indicate the existing offsite monitoring is being changed to having the signals go to a St. Al's control room. I asked for a copy of the agreement allowing this. I explained in the email that if there is no agreement in place, this will not be allowed for this building and offsite monitoring will be required.
|
Miscellaneous action | | | 10/17/2012 | | DONE |
|
|
|
Spoke to Deputy Chief Gervais regarding the monitoring for this building. He stated that he is unaware of an allowance or agreement to not have offsite monitoring. He agrees that this building is required to have offsite monitoring provided.
|
Application received | | | 10/11/2012 | | DONE |
Barbara Stitt
|
|
|
|