Miscellaneous action | | | 4/8/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 1/7/2013 | 1/7/2013 | 1/7/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 1/3/2013 | 1/4/2013 | 1/4/2013 | P | FAIL |
Troy Cobbley
|
|
|
Need the spare heads/wrench for the head box and the backflow certified.
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2012 | 12/7/2012 | 12/7/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic re-test passed for both the first and second floors.
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2012 | 12/5/2012 | 12/5/2012 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Lonnie phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2012 | 12/4/2012 | 12/4/2012 | P | NR |
Forrest France
|
|
|
Guages below 200 psi. @ approx 190.
|
INSP-Sprinkler Rough-in/Hydro | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed on both systems due to visable pressure loss.
|
INSP-Sprinkler Rough-in | 11/1/2012 | 11/1/2012 | 11/2/2012 | P | PASS |
Troy Cobbley
|
|
|
Tenting is complete. Piping is ok to cover.
|
INSP-Sprinkler Rough-in | 10/29/2012 | 10/29/2012 | 10/29/2012 | P | PART |
Forrest France
|
|
|
Overhead rough-in inspection completed. Need to verify lintel or door at second floor bathroom to meet ft2 exception or install a pendent, missing sprinkler heads at two locations. Tenting to be inspected prior to approval for cover.
|
Miscellaneous action | | | 10/24/2012 | | PEND |
|
|
|
On hold pending new 4 sprinkler calc.
|
Sprinkler Plan Check | 10/24/2012 | | 10/24/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2012 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 10/24/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 10/24/2012 | | 10/24/2012 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/24/2012 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 10/24/2012 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 10/15/2012 | | 10/24/2012 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 10/23/2012 | | |
|
|
|
|
Sprinkler Plan Check | 10/22/2012 | | 10/22/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Miscellaneous action | | | 10/22/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 10/22/2012 | | DONE |
Christina Prado
|
|
|
Called TVFP to advise resubmittals are needed
|
Miscellaneous action | | | 10/22/2012 | | DONE |
|
|
|
contractor picked up denied plans
|
Plan resubmittals received | | | 10/19/2012 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal docs and plans; routed to Tim Frost
|
Sprinkler Plan Check | 10/18/2012 | | 10/18/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 10/18/2012 | | FAIL |
Tim Frost
|
|
|
|
Telephone call | | | 10/18/2012 | | |
|
|
|
10-18-12 called Treasure Valley Fire -Brad permit needs to be picked up///dld
|
Application received | | | 10/15/2012 | | |
|
|
|
|