Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR12-00610
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 113 S AUTO DR
Project NameCalvary Chapel
Customer Number 
ePlanReviewNo
Description
The fire sprinkler scope of work consists of protecting a new church. The system is a modified grid with 1¼” branch lines, 3”, 2” & 1¼” mains. The system is supplied through 6” underground piping, 3” riser with 3” backflow preventer.

Underground piping is under permit FIR12-00490
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/23/2013 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection9/3/20139/4/20139/4/2013PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection8/29/20138/30/20138/30/2013ACANC
DetailsTroy Cobbley
Please call Perly 30 minutes prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Sprinkler Rough-in/Hydro8/28/20138/28/20138/28/2013PPASS
DetailsTroy Cobbley
OH Hydro passed
INSP-Sprinkler Rough-in/Hydro8/27/20138/27/20138/27/2013PFAIL
DetailsTroy Cobbley
Overhead hydro test failed due to visible pressure loss on the guage.
INSP-Sprinkler Rough-in/Hydro8/26/20138/26/20138/26/2013PCANC
DetailsTroy Cobbley
Overbooked
INSP-Sprinkler Rough-in8/16/20138/19/20138/19/2013APART
DetailsTroy Cobbley
Piping can be covered but several locations marked in red have upright sprinkler coverage overspaced due to insulation. Also several of the classroom closets have surface mounted light fixtures located right next to sprinkler heads. Ceiling tile will need to be removed to verify these corrections.
INSP-Sprinkler Rough-in5/28/20135/28/20135/28/2013PPASS
DetailsTroy Cobbley
The underground flush passed. Not ready for an additional cover inspection.
INSP-Sprinkler Rough-in5/8/20135/9/20135/9/2013APASS
DetailsTroy Cobbley
Hard lids ok to cover. I noed one location in the northwest corner of the building where upright sprinkler coverage is needed above one of the hardlids.
FIR-Aging Inspection3/15/20133/15/20133/15/2013 NR
DetailsTroy Cobbley
work is in progress
Plan assigned to (Tim)10/15/2012 10/30/2012 DONE
DetailsTim Frost
Sprinkler Plan Check10/30/2012 10/30/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  10/30/2012 DONE
DetailsTim Frost
Telephone call  10/30/2012 DONE
DetailsChristina Prado
Called Don to advise permit is ready and gave fees due
Permit Ready to Issue  10/30/2012 DONE
DetailsChristina Prado
Inspection Record Card- Fire10/30/2012 10/30/2012 DONE
DetailsChristina Prado
Issue and Print Permit  10/30/2012 DONE
Plan resubmittals received  10/26/2012  
DetailsTim Frost
Sprinkler Plan Check10/19/2012 10/19/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  10/19/2012 FAIL
DetailsTim Frost
Miscellaneous action  10/19/2012 DONE
DetailsTim Frost
Emailed review to contractor
Telephone call  10/19/2012 DONE
DetailsBarbara Stitt
Left voise message for Don that plans failed and need picked up and re-submitted on 10-19-12 @ 12:10pm//BAS
Application received  10/15/2012