Miscellaneous action | | | 2/14/2013 | | DONE |
|
|
|
Plans taken to records for scanning
|
INSP-Final Inspection | 1/28/2013 | 1/28/2013 | 1/28/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/15/2013 | 1/16/2013 | 1/16/2013 | P | FAIL |
Troy Cobbley
|
|
|
Need a report of the signals sent today, as-builts showing the actual wiring of the dialer to the facp and verification sent to plan review to approve this wiring, and the duct smoke detectors repaired. Need signage on the facp room door as well.
|
Fees Due Hold | 12/20/2012 | | 12/20/2012 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/19/2012 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 12/10/2012 | | 12/18/2012 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Alarm Plan Check | 12/18/2012 | | 12/18/2012 | | PASS |
Stephanie L. Cobbley
|
|
|
plan modification approved.
|
PLANS TAKEN FRONT DESK ALARM | | | 12/18/2012 | | DONE |
|
|
|
Approved plan modification documents taken to the permit technician for processing.
|
Inspection Record Card- Fire | 12/18/2012 | | 12/18/2012 | | DONE |
Darla L Downs
|
|
|
|
Permit Ready to Issue | | | 12/18/2012 | | |
|
|
|
|
Telephone call | | | 12/18/2012 | | |
|
|
|
12-18-12 called Alarmco - Jason permit ready and fee given ///dld
|
Plan resubmittals received | | | 12/10/2012 | | DONE |
|
|
|
plan mod rec'd
|
Alarm Plan Check | 12/5/2012 | | 12/5/2012 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 12/5/2012 | | DONE |
|
|
|
Approved resubmittals taken to permit technician for processing.
|
Permit Ready to Issue | | | 12/5/2012 | | |
|
|
|
|
Inspection Record Card- Fire | 12/5/2012 | | 12/5/2012 | | DONE |
Darla L Downs
|
|
|
|
Telephone call | | | 12/5/2012 | | |
|
|
|
12-5-12 called Alarmco permit ready and fee given ///dld
|
Issue and Print Permit | | | 12/5/2012 | | DONE |
|
|
|
|
Plan assigned to (Stephanie) | 11/2/2012 | | 12/5/2012 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan resubmittals received | | | 11/28/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plans and documentation; gave to Stephanie for further review
|
1st review completed | | | 11/13/2012 | | FAIL |
|
|
|
|
Alarm Plan Check | 11/13/2012 | | 11/13/2012 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans denied - see review comments and redlines
|
Miscellaneous action | | | 11/13/2012 | | DONE |
|
|
|
Emailed contractor to let them know the plans are being denied.
|
Miscellaneous action | | | 11/13/2012 | | DONE |
|
|
|
Faxed review comments to applicant
|
Miscellaneous action | | | 11/13/2012 | | DONE |
|
|
|
Plans placed in drawer at permit counter for contractor to pick up.
|
Telephone call | | | 11/6/2012 | | DONE |
|
|
|
Spoke to Alarmco regarding discrepencies in the information provided. This is a new communications technology not previously submitted to the City of Boise. I asked for an installation manual and clarification on items shown on the plans. The plans indicate internet communications with a land-line phone backup, however Alarmco stated during the phone conversation that it is wireless (similar to the AES radio) with a cell phone backup. I let them know that normally the process is to provide all information for a new communications method prior to using them in a fire alarm submital. I explained that I want time to go through the information thoroughly to determine if it is going to be allowed in our jurisdiction, to prepare adequate instruction for the inspectors, and to be able to review the plans accordingly. They said they would work on getting me the information I need.
|
Application received | | | 11/2/2012 | | DONE |
Barbara Stitt
|
|
|
|