INSP-Final Inspection | 6/28/2013 | 7/1/2013 | 7/1/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2013 | 6/28/2013 | 6/28/2013 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in | 4/30/2013 | 5/1/2013 | 5/1/2013 | A | PASS |
Troy Cobbley
|
|
|
All piping can be covered except the south "east/west" corridor and southeast room. Head installation is not complete in these two areas. Also additional sprinkler coverage will be required in the "electrical room" due to a half ceiling being installed. Also two additional dry pendants will be required behind the condensor units in the cooler.
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2013 | 5/1/2013 | 4/30/2013 | P | CANC |
Troy Cobbley
|
|
|
Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 4/22/2013 | 4/23/2013 | 4/23/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where ceiling tile can be installed to cover piping
|
INSP-Sprinkler Rough-in | 3/28/2013 | 4/1/2013 | 4/1/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for two locations marked in red where the hardlid ceilings can be installed. Also the rough-in inspection for the overhead lines passed. Not all of the drops have been installed/piped. I noted two locations where retaining straps are not bent over the truss. Also plan modifications will be needed due to additional elbows in both the 2 1/2" and 4" mains that supply the remote areas.
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2013 | 3/29/2013 | 3/29/2013 | A | NR |
Forrest France
|
|
|
Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 3/28/2013 | 3/28/2013 | 3/28/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2013 | 3/28/2013 | 3/28/2013 | P | CANC |
Troy Cobbley
|
|
|
Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Supply line flush | 3/27/2013 | 3/28/2013 | 3/28/2013 | A | CANC |
Troy Cobbley
|
|
|
Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/20/2013 | 3/22/2013 | 3/22/2013 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Supply line flush | 3/18/2013 | 3/22/2013 | 3/20/2013 | P | CANC |
Troy Cobbley
|
|
|
Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 3/18/2013 | 3/22/2013 | 3/20/2013 | P | CANC |
Troy Cobbley
|
|
|
This is an ug hydro. Robert is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 12/7/2012 | 12/10/2012 | 12/10/2012 | A | PART |
Troy Cobbley
|
|
|
The underground supply line piping is ok to cover from the building to the blow off cap. The connection to United Water is not complete at this time due to bury depth. issues.
|
Plan assigned to (Tim) | 11/15/2012 | | 12/4/2012 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/4/2012 | | 12/4/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2012 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/4/2012 | | 12/4/2012 | | DONE |
Darla L Downs
|
|
|
|
Inspection Record Card- Fire | 12/4/2012 | | 12/4/2012 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 12/4/2012 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/20/2012 | | 11/20/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 11/20/2012 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/20/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 11/20/2012 | | |
|
|
|
11-20-12 called Shilo Automatic Sprinkler -Tom permit needs to be picked up ///dld
|
Application received | | | 11/15/2012 | | |
|
|
|
|
Case Summary | | | 11/15/2012 | | DONE |
Barbara Stitt
|
|
|
|