Permit Information
Permit NumberFIR12-00681
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 800 W MAIN ST
Project Name8th & Main Twr CoreBase & Pump
Customer NumberBASEMENT PUMP
ePlanReviewYes
Description
The fire sprinkler scope of work consists of the basement and fire pump. The fire pump is rated at 750 Gpm @ 175 Psi. There will be two 6” supplies to the fire pump and two FDC connections. The fire pump is equipped with a 6” by pass and 6” hose test header. The system layout for the basement consists of a pressure reducing valve (set at 125#) a 3” loop with 1¼” branch piping. All sprinklers are quick response type. The basement also has a 4” header with (3) 4” dry pipe valves for the 3-5 floors.

The underground is under permit FIR12-00605
The standpipes is under permit FIR12-00634
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/17/201312/17/201312/18/2013PPASS
DetailsForrest France
INSP-Final Inspection12/12/201312/13/201312/13/2013APART
DetailsForrest France
C/N items include matched temp heads at an electrical room, replace hanger on added coverage, access to NW elevator machine room, floor drain function at the fire pump room.
INSP-Final Inspection11/27/201312/2/201312/3/2013APART
DetailsForrest France
Need to remove valves in the pressure sensing lines per NFPA 20, pump room still missing ventilation, floor drain does not function, final walkthrough at the basement incomplete.
INSP-Final Inspection11/19/201311/22/201311/26/2013ANR
DetailsForrest France
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
Sprinkler Plan Check11/20/2013 11/20/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  11/20/2013 DONE
DetailsTim Frost
CHANGE STATUS TO (ISS)  11/20/2013 DONE
DetailsChristina Prado
(F) Reprint permit  11/20/2013 DONE
DetailsChristina Prado
Plan resubmittals received  11/18/2013 DONE
Details
Pump Room plan modification received.
Miscellaneous action  11/15/2013 DONE
Sent email to Jim Darr

Jim,

I need a revised drawing showing the new fire pump room. Apparently it is finished. Did any sprinkler have to be relocated?

INSP-Sprinkler Rough-in10/8/201310/10/201310/10/2013APART
DetailsForrest France
Completed fire pump acceptance testing per NFPA 20. Noted fire pump room is missing required ventilation, floor drain does not function adequately, upright heads at the new west wall exceed min. distance from the wall.
Miscellaneous action  9/26/2013 DONE
Email to architect Jason Butler

Per my previous review, various letters and conversation, it was discussed that the fire pump room at 8th and main does not comply with NFPA 20. I understood that the fire pump room was to be isolated per NFPA 20 requirements. The changes will of course be required BEFORE any occupancy is permitted. The sprinklers in this area may need to be revised due to the new wall configuration. What is the status of making these changes to the fire pump room?
INSP-Sprinkler Rough-in/Hydro3/27/20133/29/20133/29/2013PPART
DetailsForrest France
For overhead hydrostatic testing of the header and supply piping.
INSP-Sprinkler Rough-in2/26/20132/27/20133/1/2013PPART
DetailsForrest France
Noted corrections at the basement level shell work only.
Issue and Print Permit  12/6/2012 DONE
uploaded copy of permit into project dox
Issue and Print Permit  12/5/2012 DONE
DetailsBarbara Stitt
Inspection Record Card- Fire12/5/2012 12/5/2012 DONE
DetailsBarbara Stitt
Issue and Print Permit  12/5/2012 DONE
DetailsBarbara Stitt
Inspection Record Card- Fire12/5/2012 12/5/2012 DONE
DetailsBarbara Stitt
Plan assigned to (Tim)11/26/2012 12/4/2012 DONE
DetailsTim Frost
Sprinkler Plan Check12/4/2012 12/4/2012 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  12/4/2012 DONE
DetailsTim Frost
Sprinkler Plan Check11/29/2012 11/29/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  11/29/2012 FAIL
DetailsTim Frost
Telephone call  11/29/2012  
11-29-12 called Shilo Automatic Sprinkler permit needs picked up ///dld
Application received  11/26/2012 DONE
DetailsBarbara Stitt