Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR12-00695
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 9101 W FAIRVIEW AVE
Project NamePETERSON TOYOTA
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration. The existing building will have two new additions and one new canopy. A new antifreeze system will be added to a canopy. The protection will be broken into two systems due to exceeding 52000 ft^2. The existing underground piping supplying the existing hydrant will be abandoned since the piping is under the footprint of the new service shop addition. A new 6” underground lead in will be brought into the building. The existing backflow preventer is located in vault at the northern edge of the parking lot. Two 6” riser supplies the project from a common 8” header with a wall PIV. This is a large facility with multiple grids
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  3/6/2014 DONE
DetailsTim Frost
Sent to Records for scanning.
INSP-Final Inspection10/29/201311/1/201310/31/2013APASS
DetailsTroy Cobbley
permit finaled
INSP-Alarm Testing10/11/201310/14/201310/14/2013AFAIL
DetailsTroy Cobbley
Interconnection of the tamper switches and flow switches with the FACP passed inspection. Forward flow tests passed as well.
INSP-Final Inspection10/10/201310/14/201310/11/2013ACANC
DetailsTroy Cobbley
kerry Phone #: ###-#### Inspection cancelled from web by: Jeff Packham
INSP-Sprinkler Rough-in/Hydro10/8/201310/9/201310/9/2013APASS
DetailsTroy Cobbley
Overhead hydro passed
INSP-Sprinkler Rough-in/Hydro10/8/201310/8/201310/8/2013PCANC
DetailsTroy Cobbley
hyro test // Kerry Phone #: ###-####
INSP-Sprinkler Rough-in10/7/201310/8/201310/8/2013APASS
DetailsTroy Cobbley
See the city approved plans for locations with todays date where additional piping is ok to cover.
INSP-Sprinkler Rough-in9/10/20139/11/20139/11/2013APASS
DetailsTroy Cobbley
Lounge area piping is ok to cover..
INSP-Sprinkler Rough-in8/28/20138/29/20138/29/2013APASS
DetailsTroy Cobbley
See the city approved plans for new areas where piping is ok to cover.
INSP-Final Inspection8/22/20138/23/20138/23/2013APART
DetailsTroy Cobbley
Sprinkler work in the lube bay expansion and the Service Shop expansion is complete except for as-builts showing the re-routing of mains. Also the Lexus drive through/canopy fire sprinkler system is now active so it can be used for driving through.
INSP-Sprinkler Rough-in/Hydro7/26/20137/26/20137/26/2013PPART
DetailsForrest France
UG fire supply line hydrostatic test completed satisfactory.
INSP-Sprinkler Rough-in/Hydro7/24/20137/25/20137/25/2013APART
DetailsForrest France
Overhead hydrostatic test of the new wet system serving the lube bay completed
INSP-Supply line flush7/23/20137/23/20137/23/2013PPASS
DetailsTroy Cobbley
The remaining underground is ok for cover and the flush for the two IBR's and the fire hydrant passed.
INSP-Sprinkler Rough-in7/22/20137/23/20137/23/2013APASS
DetailsTroy Cobbley
See the city approved plans for location where underground supply piping can be covered.
INSP-Sprinkler Rough-in7/22/20137/22/20137/22/2013PCANC
DetailsTroy Cobbley
Cancelled due to being over booked. Rescheduled for tomorrow.
INSP-Sprinkler Rough-in7/3/20137/5/20137/5/2013APASS
DetailsTroy Cobbley
See the city approved plans for areas where rough-in passed and in some locations the piping can be covered. Still need seismic bracing for the brachline piping located in the Car Wash.
INSP-Sprinkler Rough-in7/2/20137/3/20137/3/2013APART
DetailsTroy Cobbley
See the city approved plans for rough-in inspection locations for today. Mostly passed but seismic restraint for the branchlines is missing is all location inspected today. Will need as-bults showing the new routing of the two 6" main in the service area. The car wash area piping size as installed does not match the approved plans.
INSP-Final Inspection5/7/20135/7/20135/7/2013PPART
DetailsTroy Cobbley
Piping in the "Bull Pen" and "Accounting" areas is completed.
INSP-Sprinkler Rough-in/Hydro5/7/20135/7/20135/7/2013PPASS
DetailsTroy Cobbley
Overhead hydro test of the anti-freeze loop passed
INSP-Sprinkler Rough-in5/2/20135/3/20135/3/2013APART
DetailsForrest France
UG fire supply line IBR only- inspected and approved for cover. Plans initialed and dated.
INSP-Sprinkler Rough-in5/2/20135/3/20135/3/2013APART
DetailsForrest France
Refer to clouded and dated area on stamped plan set for overhead work inspected for cover approval.
INSP-Sprinkler Rough-in5/1/20135/2/20135/2/2013APASS
DetailsTroy Cobbley
south canopy at lexus showroom is ok to cover the sprinkler piping. Siesmic branchline restraints and retaining straps have been provided.
INSP-Final Inspection5/1/20135/2/20135/2/2013APART
DetailsTroy Cobbley
Area #1 lexus showroom/lounge/cafe, Area #2 mezzanine upper/lower sprinkler work is complete.
INSP-Sprinkler Rough-in4/17/20134/17/20134/17/2013PPASS
DetailsTroy Cobbley
See the city approved plans for locatins in the northwest corner of the building marked "ok" where sprinkler piping can be covered.
INSP-Sprinkler Rough-in4/10/20134/10/20134/10/2013PPASS
DetailsTroy Cobbley
See the city approved plans for location marked in red where the sprinkler piping can be covered.
Plan assigned to (Tim)12/4/2012 4/3/2013 DONE
DetailsTim Frost
Sprinkler Plan Check4/3/2013 4/3/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  4/3/2013 DONE
DetailsTim Frost
Permit Ready to Issue  4/3/2013 DONE
Permit Ready to Issue  4/3/2013  
Inspection Record Card- Fire4/3/2013 4/3/2013 DONE
DetailsDarla L Downs
Issue and Print Permit  4/3/2013 DONE
Sprinkler Plan Check3/7/2013 3/7/2013 FAIL
DetailsTim Frost
Early Start  2/12/2013 PASS
Telephone call  12/18/2012 DONE
DetailsChristina Prado
called Jeff to advise plans have been denied and need to be picked up
Sprinkler Plan Check12/17/2012 12/17/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
Miscellaneous action  12/17/2012 DONE
DetailsTim Frost
Emailed review to contractor
Plan resubmittals received  12/14/2012  
Sprinkler Plan Check12/13/2012 12/13/2012 FAIL
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
1st review completed  12/13/2012 FAIL
DetailsTim Frost
Telephone call  12/13/2012 DONE
DetailsTisha Gallop
called Tim Anderson and left vm failed plans at front desk to pick up
Miscellaneous action  12/12/2012 DONE
Project was on hold by the fp contractor from 12-04-12 to 12-12-12
Miscellaneous action  12/10/2012 PEND
Email to Jeff Packham

Just a reminder Jeff, I still have this project on hold per your request.

Cordially,

Tim Frost, S.E.T.
Fire Sprinkler Plans Examiner
Fire Plans Examiner
Fire Inspector

City of Boise
tfrost@cityofboise.org
###-####
Application received  12/4/2012