Miscellaneous action | | | 3/6/2014 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 10/29/2013 | 11/1/2013 | 10/31/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 10/11/2013 | 10/14/2013 | 10/14/2013 | A | FAIL |
Troy Cobbley
|
|
|
Interconnection of the tamper switches and flow switches with the FACP passed inspection. Forward flow tests passed as well.
|
INSP-Final Inspection | 10/10/2013 | 10/14/2013 | 10/11/2013 | A | CANC |
Troy Cobbley
|
|
|
kerry Phone #: ###-#### Inspection cancelled from web by: Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2013 | 10/9/2013 | 10/9/2013 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2013 | 10/8/2013 | 10/8/2013 | P | CANC |
Troy Cobbley
|
|
|
hyro test // Kerry Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/7/2013 | 10/8/2013 | 10/8/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations with todays date where additional piping is ok to cover.
|
INSP-Sprinkler Rough-in | 9/10/2013 | 9/11/2013 | 9/11/2013 | A | PASS |
Troy Cobbley
|
|
|
Lounge area piping is ok to cover..
|
INSP-Sprinkler Rough-in | 8/28/2013 | 8/29/2013 | 8/29/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new areas where piping is ok to cover.
|
INSP-Final Inspection | 8/22/2013 | 8/23/2013 | 8/23/2013 | A | PART |
Troy Cobbley
|
|
|
Sprinkler work in the lube bay expansion and the Service Shop expansion is complete except for as-builts showing the re-routing of mains. Also the Lexus drive through/canopy fire sprinkler system is now active so it can be used for driving through.
|
INSP-Sprinkler Rough-in/Hydro | 7/26/2013 | 7/26/2013 | 7/26/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2013 | 7/25/2013 | 7/25/2013 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the new wet system serving the lube bay completed
|
INSP-Supply line flush | 7/23/2013 | 7/23/2013 | 7/23/2013 | P | PASS |
Troy Cobbley
|
|
|
The remaining underground is ok for cover and the flush for the two IBR's and the fire hydrant passed.
|
INSP-Sprinkler Rough-in | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location where underground supply piping can be covered.
|
INSP-Sprinkler Rough-in | 7/22/2013 | 7/22/2013 | 7/22/2013 | P | CANC |
Troy Cobbley
|
|
|
Cancelled due to being over booked. Rescheduled for tomorrow.
|
INSP-Sprinkler Rough-in | 7/3/2013 | 7/5/2013 | 7/5/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas where rough-in passed and in some locations the piping can be covered. Still need seismic bracing for the brachline piping located in the Car Wash.
|
INSP-Sprinkler Rough-in | 7/2/2013 | 7/3/2013 | 7/3/2013 | A | PART |
Troy Cobbley
|
|
|
See the city approved plans for rough-in inspection locations for today. Mostly passed but seismic restraint for the branchlines is missing is all location inspected today. Will need as-bults showing the new routing of the two 6" main in the service area. The car wash area piping size as installed does not match the approved plans.
|
INSP-Final Inspection | 5/7/2013 | 5/7/2013 | 5/7/2013 | P | PART |
Troy Cobbley
|
|
|
Piping in the "Bull Pen" and "Accounting" areas is completed.
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2013 | 5/7/2013 | 5/7/2013 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test of the anti-freeze loop passed
|
INSP-Sprinkler Rough-in | 5/2/2013 | 5/3/2013 | 5/3/2013 | A | PART |
Forrest France
|
|
|
UG fire supply line IBR only- inspected and approved for cover. Plans initialed and dated.
|
INSP-Sprinkler Rough-in | 5/2/2013 | 5/3/2013 | 5/3/2013 | A | PART |
Forrest France
|
|
|
Refer to clouded and dated area on stamped plan set for overhead work inspected for cover approval.
|
INSP-Sprinkler Rough-in | 5/1/2013 | 5/2/2013 | 5/2/2013 | A | PASS |
Troy Cobbley
|
|
|
south canopy at lexus showroom is ok to cover the sprinkler piping. Siesmic branchline restraints and retaining straps have been provided.
|
INSP-Final Inspection | 5/1/2013 | 5/2/2013 | 5/2/2013 | A | PART |
Troy Cobbley
|
|
|
Area #1 lexus showroom/lounge/cafe, Area #2 mezzanine upper/lower sprinkler work is complete.
|
INSP-Sprinkler Rough-in | 4/17/2013 | 4/17/2013 | 4/17/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locatins in the northwest corner of the building marked "ok" where sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 4/10/2013 | 4/10/2013 | 4/10/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location marked in red where the sprinkler piping can be covered.
|
Plan assigned to (Tim) | 12/4/2012 | | 4/3/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/3/2013 | | 4/3/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/3/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/3/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 4/3/2013 | | 4/3/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 4/3/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/7/2013 | | 3/7/2013 | | FAIL |
Tim Frost
|
|
|
|
Early Start | | | 2/12/2013 | | PASS |
|
|
|
|
Telephone call | | | 12/18/2012 | | DONE |
Christina Prado
|
|
|
called Jeff to advise plans have been denied and need to be picked up
|
Sprinkler Plan Check | 12/17/2012 | | 12/17/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Miscellaneous action | | | 12/17/2012 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Plan resubmittals received | | | 12/14/2012 | | |
|
|
|
|
Sprinkler Plan Check | 12/13/2012 | | 12/13/2012 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/13/2012 | | FAIL |
Tim Frost
|
|
|
|
Telephone call | | | 12/13/2012 | | DONE |
Tisha Gallop
|
|
|
called Tim Anderson and left vm failed plans at front desk to pick up
|
Miscellaneous action | | | 12/12/2012 | | DONE |
|
|
|
Project was on hold by the fp contractor from 12-04-12 to 12-12-12
|
Miscellaneous action | | | 12/10/2012 | | PEND |
|
|
|
Email to Jeff Packham
Just a reminder Jeff, I still have this project on hold per your request.
Cordially,
Tim Frost, S.E.T.
Fire Sprinkler Plans Examiner
Fire Plans Examiner
Fire Inspector
City of Boise
tfrost@cityofboise.org
###-####
|
Application received | | | 12/4/2012 | | |
|
|
|
|