INSP-Final Inspection | 1/18/2013 | 1/22/2013 | 1/22/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2013 | 1/17/2013 | 1/17/2013 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro and rough-in passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2013 | 1/17/2013 | 1/17/2013 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test for the new storage area piping failed due to visable drop on the pressure guage. Also the earthquake attachments do not match the city approved drawings and don't have through bolts for the wood members per NFPA 13 Chapter 9.
|
INSP-Sprinkler Rough-in/Hydro | 1/16/2013 | 1/16/2013 | 1/16/2013 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints. jeremy Phone #: ###-####
|
Sprinkler Plan Check | 12/27/2012 | | 12/27/2012 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/27/2012 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/27/2012 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/27/2012 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 12/27/2012 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 12/27/2012 | | 12/27/2012 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 12/19/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 19 2012 9:34AM
|