INSP-Final Inspection | 3/14/2013 | 3/15/2013 | 3/15/2013 | P | PASS |
Forrest France
|
|
|
Fire alarm testing completed and passed after adjustments made while on site. Permit finaled.
|
Permit Ready to Issue | | | 2/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue and Print Permit | | | 2/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Fire | 2/7/2013 | | 2/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 2/6/2013 | | PASS |
|
|
|
|
Alarm Plan Check | 2/6/2013 | | 2/6/2013 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 2/6/2013 | | DONE |
|
|
|
updated in project dox
|
Miscellaneous action | | | 1/30/2013 | | DONE |
|
|
|
Received requested information for pre-screen
|
Plan assigned to (Stephanie) | 1/30/2013 | | 1/30/2013 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Application received | | | 1/8/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 8 2013 9:48AM
|
Miscellaneous action | | | 1/8/2013 | | DONE |
|
|
|
The pre-screen was not accepted. The application indicates the applicant as the designer, however the building set includes fire alarm drawings stamped by Thad Mason. These plans must be reviewed by the designer of record prior to submitting the plans to the City of Boise. The fire alarm plans must either be stamped by the designer or a letter from the designer must be provided indicating the plans have met the design intent. The application and checklist must be revised to indicate the correct designer information and the checkbox selected indicating you have provided the letter from the engineer. The revised application and checklist must be emailed to scobbley@cityofboise.org (please do not go back through e-apply). The drawings must be re-uploaded once they have been reviewed by the engineer.
|