Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 7/23/2013 | 7/25/2013 | 7/26/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 7/3/2013 | 7/3/2013 | 7/3/2013 | P | PASS |
Troy Cobbley
|
|
|
Vaulted ceiling area is ok to cover at 2018
|
INSP-Sprinkler Rough-in | 6/25/2013 | 6/26/2013 | 6/26/2013 | A | PART |
Troy Cobbley
|
|
|
All piping can be covered except the piping above the vaulted ceiling. The tenting here is not complete.
|
INSP-Sprinkler Rough-in | 6/3/2013 | 6/4/2013 | 6/4/2013 | A | PASS |
Troy Cobbley
|
|
|
Tenting inspection is passed at 2030. Sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 5/21/2013 | 5/21/2013 | 5/21/2013 | P | PASS |
Troy Cobbley
|
|
|
See residence with green tag that is ok to cover sprinkler piping.
|
INSP-Conference | 5/20/2013 | 5/20/2013 | 5/20/2013 | P | DONE |
Troy Cobbley
|
|
|
Frank and I discussed the relocation of the electric alarm bells to the nearest point ot the building to the street. Per Potter Electric the bell must be mounted vertical with the weather proof back boxes (per NEC).
|
INSP-Sprinkler Rough-in | 4/17/2013 | 4/17/2013 | 4/17/2013 | P | PASS |
Troy Cobbley
|
|
|
Another residence is ok to cover. See sticker on window of second residence on south end of complex.
|
INSP-Sprinkler Rough-in | 4/16/2013 | 4/17/2013 | 4/17/2013 | A | FAIL |
Troy Cobbley
|
|
|
Tenting was not complete
|
INSP-Sprinkler Rough-in | 4/12/2013 | 4/12/2013 | 4/12/2013 | A | PASS |
Troy Cobbley
|
|
|
Tenting inspection for cover passed for east most residence.
|
INSP-Sprinkler Rough-in | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | CANC |
Troy Cobbley
|
|
|
Overbooked . Lonnie is going to reschedule.
|
INSP-Sprinkler Rough-in | 4/9/2013 | 4/9/2013 | 4/9/2013 | P | CANC |
Troy Cobbley
|
|
|
Per lonny to be canceled Phone #: ###-####
|
INSP-Sprinkler Rough-in | 4/4/2013 | 4/4/2013 | 4/4/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for residence where the rough-in is passed. Tenting has not been completed yet.
|
INSP-Sprinkler Rough-in/Hydro | 4/1/2013 | 4/1/2013 | 4/2/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for residences that are either rough-in approved or approved for cover.
|
Issue and Print Permit | | | 2/14/2013 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 1/23/2013 | | 2/7/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/7/2013 | | 2/7/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Fire | 2/7/2013 | | 2/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 2/7/2013 | | DONE |
Tisha Gallop
|
|
|
called Jon and told him permit is ready and fees.
|
Plan resubmittals received | | | 2/6/2013 | | |
|
|
|
|
Telephone call | | | 1/23/2013 | | DONE |
Barbara Stitt
|
|
|
Called Jeff and told him that permit failed needs picked up and resubmitted on 1-23-13 @ 8:40am
|
Plan assigned to (Tim) | 1/16/2013 | | 1/23/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/23/2013 | | 1/23/2013 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are annotations on the plans.
|
1st review completed | | | 1/23/2013 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 1/16/2013 | | |
|
|
|
|