INSP-Final Inspection | 4/29/2013 | 4/30/2013 | 4/30/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 4/29/2013 | 4/30/2013 | 4/30/2013 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test and forward flush passed
|
INSP-Conference | 4/25/2013 | 4/25/2013 | 4/25/2013 | P | PASS |
Troy Cobbley
|
|
|
The modified 4" pipe routing below the mezzanine is passed.
|
Override - Parcel Holds | 4/25/2013 | 1/1/1900 | 4/25/2013 | | |
|
|
|
fir conf
|
Miscellaneous action | | | 4/24/2013 | | DONE |
|
|
|
Jeff P submitted a small change of rerouting the main around some stairs near column line C. The change looks fine to me.
|
INSP-Sprinkler Rough-in | 4/19/2013 | 4/19/2013 | 4/19/2013 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in passed. Baffles are needed between many of the sprinkler heads below the mezzanine since a min. 8'-0" is needed between the heads. Jeff and I discussed options.
|
INSP-Sprinkler Rough-in | 4/11/2013 | 4/12/2013 | 4/12/2013 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping above hardlids is ok to cover
|
INSP-Sprinkler Rough-in | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. Troy is going to reschedule
|
Sprinkler Plan Check | 4/11/2013 | | 4/11/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/11/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 4/11/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 4/11/2013 | | 4/11/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 1/30/2013 | | 1/30/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/24/2013 | | 1/24/2013 | | FAIL |
Tim Frost
|
|
|
|
Early Start | | | 1/23/2013 | | PASS |
|
|
|
See documents
|
1st review completed | | | 1/23/2013 | | FAIL |
|
|
|
|
Application received | | | 1/22/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 22 2013 1:32PM
|