Description
The fire sprinkler scope of work consists of protecting a three level building. Some of the existing fire protection will remain. New ceilings being installed; new floor control valves are being added. Each floor is protected by a grid type system. All sprinklers are to be changed to quick response type.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/14/20138/15/20138/15/2013APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection8/12/20138/14/20138/14/2013AFAIL
DetailsTroy Cobbley
Permit will be able to final when the ceiling and pendant is installed in the electrical/mechanical room.
INSP-Sprinkler Rough-in/Hydro8/7/20138/9/20138/9/2013APART
DetailsForrest France
Overhead hydrostatic test for the first and second floor wet systems passed.
INSP-Sprinkler Rough-in8/7/20138/8/20138/8/2013PPASS
DetailsTroy Cobbley
Rough to cover on first and second floors. See the city approved plans for areas marked "ok" in red. I noted one electrical room missing an upright sprinkler head.
INSP-Sprinkler Rough-in8/5/20138/6/20138/6/2013APASS
DetailsTroy Cobbley
See the city approved plans for additional areas on the second floor where sprinkler piping can be covered. First floor needs the ceiling tile removed so that a rough-in inspection can be performed.
INSP-Sprinkler Rough-in7/12/20137/15/20137/15/2013PPASS
DetailsTroy Cobbley
Rough to cover passed for areas marked ok on the second floor.
INSP-Sprinkler Rough-in7/11/20137/11/20137/12/2013PPASS
DetailsTroy Cobbley
Cover inspection for remainder of hard lid ceilings on the second floor passed except for the restrooms in the northwest corner
INSP-Sprinkler Rough-in7/8/20137/8/20137/8/2013PPASS
DetailsTroy Cobbley
See the city approved plans locatons marked "ok" where sprinkler piping can be covered at hard lid area.
INSP-Sprinkler Rough-in6/24/20136/24/20136/24/2013PPASS
DetailsTroy Cobbley
See the city approved plans for location on the west end of the second floor where piping is ok to cover.
INSP-Sprinkler Rough-in6/19/20136/20/20136/20/2013PPART
DetailsForrest France
Marked and dated locations on plans at the 1st and 2nd floor sheetrock lid areas including the mens and womens restrooms, kitchen and storage room okay for cover. Previous correction items at the basement including the painted upright and one missing head completed.
INSP-Sprinkler Rough-in/Hydro5/22/20135/22/20135/22/2013PPASS
DetailsTroy Cobbley
The 200lb hydro on the basement system passed. Sprinkler rough-in for the basement passed inspection and the remaining ceiling tile areas can be installed. I noted one location that an upright sprinkler needs to be installed as per plans, one painted head that needs replaced and one bent all thread rod that needs replaced. Also the remaining hardlids, except for the unfinished restrooms, on the first floor can be installed to cover the sprinkler piping.
INSP-Sprinkler Rough-in5/14/20135/15/20135/15/2013APASS
DetailsTroy Cobbley
Rough to cover in basement and first floor for piping above the hardlids passed. See the city approved plans for exact locations.
INSP-Sprinkler Rough-in5/7/20135/7/20135/7/2013APASS
DetailsTroy Cobbley
Rough-in of the remainder of hard lid ceilings in basement is passed. Piping can be covered. See the city approved plans for locations marked "ok" in red.
INSP-Sprinkler Rough-in5/3/20135/6/20135/6/2013APASS
DetailsTroy Cobbley
Rough-in inspection on the hard lids in the basement restrooms passed. Piping can be covered (already had been)
Permit Ready to Issue  5/2/2013  
Inspection Record Card- Fire5/2/2013 5/2/2013 DONE
DetailsDarla L Downs
Issue and Print Permit  5/2/2013 DONE
Sprinkler Plan Check4/30/2013 4/30/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  4/30/2013 DONE
DetailsTim Frost
INSP-Sprinkler Rough-in4/11/20134/12/20134/12/2013ADONE
DetailsTroy Cobbley
Inspection was actually for a conference to discuss the duct work causing obstructions to the sprinkler system. I refered to section 8.6.5.2.1.3 of NFPA 13.
Sprinkler Plan Check1/30/2013 1/30/2013 PASS
DetailsTim Frost
Please, see attached comments.
There are NO annotations on the plans.
PLANS/APPL TAKEN TO FRONT DESK  1/30/2013 DONE
DetailsTim Frost
Permit Ready to Issue  1/30/2013 DONE
DetailsChristina Prado
Issue and Print Permit  1/30/2013 DONE
DetailsChristina Prado
Inspection Record Card- Fire1/30/2013 1/30/2013 DONE
DetailsChristina Prado
Sprinkler Plan Check1/28/2013 1/28/2013 FAIL
DetailsTim Frost
Please, see attached comments.
There are annotations on the plans.
1st review completed  1/28/2013 FAIL
DetailsTim Frost
Plan assigned to (Tim)1/28/2013 1/28/2013 DONE
DetailsTim Frost
Application received  1/24/2013 DONE
Application submitted via PDS Online on Jan 24 2013 5:37PM