Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR13-00070
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 5831 W FRANKLIN RD
Project NameOnce More Super Store
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of protecting and existing building. The interior of the store is designed as a wet grid with 2½x2”x1¼, with a 6” underground, 3” backflow and 3” riser. There is also a 2” dry pipe system for the canopy.

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/20/20135/20/20135/20/2013PPASS
DetailsTroy Cobbley
Permit finaled. Forward flush passed.
INSP-Sprinkler Rough-in/Hydro5/9/20135/10/20135/10/2013PPASS
DetailsTroy Cobbley
Wet system hydro test passed
INSP-Sprinkler Rough-in/Hydro5/8/20135/9/20135/9/2013APART
DetailsTroy Cobbley
The underground and dry system hydro tests passed. The wet system failed again. The previous correction items have been addressed.
INSP-Sprinkler Rough-in/Hydro5/8/20135/8/20135/8/2013PFAIL
DetailsTroy Cobbley
Wet, dry and UG hydro tests failed due to visible drop in pressure on the guages.
CHANGE STATUS TO (ISS)  3/26/2013 DONE
DetailsTisha Gallop
issued plan mod
Sprinkler Plan Check3/25/2013 3/25/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/25/2013 DONE
DetailsTim Frost
Permit Ready to Issue  3/25/2013 DONE
INSP-Sprinkler Rough-in/Hydro3/14/20133/15/20133/15/2013PFAIL
DetailsTroy Cobbley
Hydro test of the wet system failed due to visable leakage at the drain weld on the riser. Earth quake bracing needs to be modifed as discussed and connected to the main piping instead of the lateral bracing. Plans need to be resubmitted showing the actual grid piping layout. We were unable to get the dry system to pump up to perform a hydro test. Rough-in inspection for the piping as installed passed.
INSP-Supply line flush3/11/20133/11/20133/11/2013PPASS
DetailsTroy Cobbley
Underground supply line flush passed
INSP-Supply line flush3/8/20133/8/20133/8/2013PFAIL
DetailsTroy Cobbley
United Water did not turn on the supply main so that we could perform the flush
INSP-Sprinkler Rough-in3/1/20133/1/20133/1/2013PPART
DetailsForrest France
Remainder of UG fire supply line okay for cover.
FIR-Aging Inspection3/1/20133/1/20133/1/2013APART
DetailsTroy Cobbley
The underground supply piping from the point of connection to the building foundation is ok to cover.
Permit Ready to Issue  2/20/2013 DONE
DetailsChristina Prado
Issue and Print Permit  2/20/2013 DONE
DetailsChristina Prado
Inspection Record Card- Fire2/20/2013 2/20/2013 DONE
DetailsChristina Prado
Plan assigned to (Tim)2/19/2013 2/19/2013 DONE
DetailsTim Frost
Sprinkler Plan Check2/19/2013 2/19/2013 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  2/19/2013 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  2/19/2013 DONE
DetailsTim Frost
Permit Ready to Issue  2/19/2013 DONE
Application received  2/14/2013 DONE
Application submitted via PDS Online on Feb 14 2013 5:08PM