Case Summary | | | 6/1/2016 | | DONE |
|
|
|
|
INSP-Final Inspection | 4/24/2013 | 4/26/2013 | 4/26/2013 | A | PASS |
Forrest France
|
|
|
Final walkthrough completed, inspection passed. Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 4/19/2013 | 4/19/2013 | 4/19/2013 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro passed. Rough-in inspection passed for the most part. Need to verify tie-ins to the existing system and verify that flexible cplgs get installed at the wall penatrations.
|
Sprinkler Plan Check | 4/2/2013 | | 4/2/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/2/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/2/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 4/2/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 4/2/2013 | | 4/2/2013 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 3/8/2013 | | 3/8/2013 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/20/2013 | | 2/20/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 2/20/2013 | | FAIL |
|
|
|
|
Plan assigned to (Tim) | 2/19/2013 | | 2/19/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 2/16/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 16 2013 9:08AM
|