Permit Information
Permit NumberFIR13-00075
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 3201 W AIRPORT WAY
Project NameBoise Airport Parking
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of adding (6) manual dry standpipes to a new parking garage and adding one new manual dry standpipe to an existing parking garage. The new parking garage will be supplied from two FDC located on opposite sides of the building. A new 6” loop will be installed on the lower level. Each new standpipe will have (3) hose connections on the intermediate levels.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/25/201311/25/201311/25/2013PPASS
DetailsForrest France
Fire sprinkler permit work okayed for final. Need to provide signage at the new FDC's per plan review note. *To be finished prior to building permit final.
INSP-Sprinkler Rough-in/Hydro11/25/201311/25/201311/25/2013PCANC
DetailsForrest France
Please call Perly 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Final Inspection11/22/201311/22/201311/25/2013PNR
DetailsForrest France
Inspection completed 11/22. Missing approved plans on site. Noted missing bracing and hanger at the east standpipe system addition.
INSP-Sprinkler Rough-in/Hydro11/18/201311/19/201311/19/2013PPART
DetailsForrest France
Overhead hydrostatic test of new system piping completed and passed.
INSP-Supply line flush11/13/201311/14/201311/14/2013APASS
DetailsTroy Cobbley
Underground lines flush on both sides of the building. Next inspection verify the check valve was changed to the correct direction.
INSP-Supply line flush11/12/201311/14/201311/13/2013PCANC
DetailsForrest France
Please call Tyler 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Supply line flush11/11/201311/13/201311/12/2013PCANC
DetailsForrest France
Please schedule flush and call Tyler 30 mins prior Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
INSP-Sprinkler Rough-in3/19/20133/20/20133/21/2013APART
DetailsForrest France
UG work okayed for cover at the south and north sides below floor slabs. Noted FDC's are installed approx. 15' from the structure- approved plans indicate 50'.
Permit Ready to Issue  3/19/2013 DONE
Inspection Record Card- Fire3/19/2013 3/19/2013 DONE
DetailsTisha Gallop
Issue and Print Permit  3/19/2013 DONE
Sprinkler Plan Check3/18/2013 3/18/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/18/2013 DONE
DetailsTim Frost
Sprinkler Plan Check3/12/2013 3/12/2013 FAIL
DetailsTim Frost
1st review completed  3/12/2013 FAIL
Miscellaneous action  3/12/2013 DONE
DetailsTim Frost
Emailed review to contractor
Plan assigned to (Tim)2/25/2013 2/25/2013 DONE
DetailsTim Frost
Application received  2/20/2013 DONE
Application submitted via PDS Online on Feb 20 2013 9:12AM