INSP-Final Inspection | 6/6/2013 | 6/7/2013 | 6/7/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. I had the contractor change the horn strobe in the first floor restroom to a strobe only to solve a sync problem.
|
INSP-Final Inspection | 6/5/2013 | 6/6/2013 | 6/6/2013 | A | FAIL |
Troy Cobbley
|
|
|
Need all of the notification circuits tested and updated as-builts provided prior to a final sign off.
|
INSP-Final Inspection | 6/4/2013 | 6/5/2013 | 6/5/2013 | A | FAIL |
Troy Cobbley
|
|
|
Testing continued today on the induct detectors on the first floor that control the hvac system and fire smoke dampers. See the city approved plans for devices marked "ok" in red.
|
Miscellaneous action | | | 6/4/2013 | | DONE |
|
|
|
Our Fire Alarm plan reviewer, Lee Meredith, has evaluated your request and determined that providing updated plans (as-built shop drawings) will be sufficient. As mentioned in your comments, these as-built plans will be required to be onsite and available for the PDS/Fire field inspector in order to conduct the final inspection. Final approval will be subject to satisfactory field inspection by the PDS/Fire inspector of all required components and modifications to modified alarm circuits.
|
INSP-Alarm Testing | 5/31/2013 | 6/3/2013 | 6/3/2013 | A | DONE |
Troy Cobbley
|
|
|
Finished the fire/smoke dampers on the second floor. Also performed walk through of the first floor to address any potential problems. It appears plan modifications will be needed due to additional initiating devices, additional notification devices, relocated initiating devices and NAC panels.
|
INSP-Alarm Testing | 5/30/2013 | 5/31/2013 | 5/31/2013 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was for the second floor. We verified spacing on all audio/visuals. Found several tht needed adjustment. Also five horns need to be changed to horn/strobes due to ceiling obstructions. Testing of the duct smoke detectors for hvac shutdown passed. It appears the fire/smoke dampers are wired backwards and access may be limited on some which will need to be addressed prior to the next inspection.
|
INSP-Alarm Testing | 5/30/2013 | 5/30/2013 | 5/30/2013 | A | FAIL |
Troy Cobbley
|
|
|
No approved plans on site. We all agreed to reschedule for tomorrow morning.
|
Permit Ready to Issue | | | 3/20/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 3/20/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 3/20/2013 | | 3/20/2013 | | DONE |
Christina Prado
|
|
|
|
Alarm Plan Check | 3/18/2013 | | 3/18/2013 | | PASS |
Stephanie L. Cobbley
|
|
|
resubmittals approved with review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 3/18/2013 | | DONE |
|
|
|
updated in project dox
|
1st review completed | | | 3/6/2013 | | FAIL |
|
|
|
|
Alarm Plan Check | 3/6/2013 | | 3/6/2013 | | FAIL |
Stephanie L. Cobbley
|
|
|
plans denied - see review comments and mark-ups
|
Miscellaneous action | | | 3/6/2013 | | DONE |
|
|
|
updated project dox
|
Miscellaneous action | | | 2/26/2013 | | DONE |
|
|
|
SimplexGrinnell emailed a request to 'swap' the review order with FIR13-00087 that they submitted today.
|
Miscellaneous action | | | 2/25/2013 | | DONE |
|
|
|
e-PlanReview prescreen accepted
|
Plan assigned to (Stephanie) | 2/25/2013 | | 2/25/2013 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Application received | | | 2/22/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 22 2013 10:25AM
|