Permit Information
Permit NumberFIR13-00086
StatusFinaled
Name TRI STATE ELECTRIC
Site Address 12601 W BRIDGER ST
Project NameIDAHO POWER-BOISE CENTER WEST
Customer Number 
ePlanReviewNo
Description
This fire alarm permit is to replace the existing required fire alarm system with a new required manual fire alarm system per owner’s request. This permit scope of work includes sprinkler system monitoring (dry and wet systems), a remote annunciator panel, pull stations in each of the two riser rooms, smoke detectors above the panels, full notification, monitoring existing VESDA systems, access control door release on general alarm, and duct detectors w/relays for HVAC monitoring/shutdown.
Associated building permit: BLD12-02338
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in/Hydro9/20/20169/20/20169/20/2016PCANC
DetailsTroy Cobbley
Geoff Phone #: ###-####-please call to meet for access
INSP-Final Inspection9/20/20169/20/20169/20/2016PPASS
DetailsTroy Cobbley
Permit finaled. Fire alarm contractor was not there. I did not receive nfpa 72
INSP-Final Inspection1/16/20161/16/20161/16/2016AFAIL
DetailsJim Page
Inspection consisted of checking interface between clean agent system panel to main fire alarm panel, clean agent panel reported to main fire alarm panel with correct addressing. Verified low air alarm, verified solenoid activation for pre-action valve trip, verified tamper valves on west pre-action as well as wet system tamper valves on west side fire sprinkler systems. Water flow pressure switch for pre-action system did not report as a water flow, reported to panel as a supervisory, water flow on pre-action needs to report as (latching) general fire alarm. Inspected east side pre-action system, verified low air alarm, verified water flow pressure switch for east pre-action with alarm test line, could not get pre-action solenoid to activate, had low air alarm as well as three smoke detectors (photo smokes in server room) in alarm with no solenoid activation. Exterior fire bell did not activate with water flow on pre-action systems, exterior bells with associated systems must ring with water flow. Contractor will reschedule inspection when items are repaired.
INSP-Final Inspection6/12/20146/16/20146/16/2014PFAIL
DetailsTroy Cobbley
For final I need the solenoid (low air, water flow) for both deluge systems verified.
INSP-Final Inspection8/28/20138/30/20138/30/2013AFAIL
DetailsTroy Cobbley
Need revised as-builts showing the 110 cd strobes and the deluge system solenoids, the west deluge system flow/pressure switch is reporting as a PIV supervisory and the Low Air pressure switch did not report at all. Waiting on the solenoid switch for the east deluge system as well.
INSP-Final Inspection8/28/20138/29/20138/29/2013AFAIL
DetailsTroy Cobbley
See the city approved plans for locations where strobes need to be relocated due to being overspaced and mounted outside of their listing. Additional devices will be required in acouple of locations. No testing of the a/v devices took place.
INSP-Final Inspection5/15/20135/16/20135/16/2013APART
DetailsTroy Cobbley
See the city approved fire alarm plans for locations tested and passed today. Area was roughly the Orange hi-lighted, dated 5/15, area on the general contractors phasing plan.
INSP-Sprinkler Rough-in5/14/20135/15/20135/15/2013PCANC
DetailsTroy Cobbley
Next phase is not ready for a final yet. I found overspaced audio/visual devices and in one location a device that is not wired up yet. Will be rescheduled.
INSP-Final Inspection4/29/20134/30/20134/30/2013PPART
DetailsTroy Cobbley
Fire alarm device testing in the LSO area passed inspection.
INSP-Final Inspection4/19/20134/22/20134/22/2013PPART
DetailsTroy Cobbley
See the city approved plans for location, clouded in red, where the fire alarm system has been inspected and passed. Per Jeremy with Alta Construction this is the first phase they are requesting occupancy.
INSP-Conference4/22/20134/22/20134/22/2013ADONE
DetailsTroy Cobbley
Myself, the alarm contractor and the electrician discussed the overspace ceiling mounted a/v' in the main corridor and womens restroom. Also the manual pull station in the mechanical room is mounted too high. Ceiling tile will need to be installed at the facp for the containment of smoke.
INSP-Conference4/1/20134/1/20134/2/2013PDONE
DetailsTroy Cobbley
I spoke with both the general contractor and the electrician about contacting the fire dept for approval for phasing the project and partial occupancy.
Miscellaneous action  3/28/2013 DONE
Recieved an email from Rob Ahten w/ Protex stating that Idaho Power would like to move into a portion of this building prior to completing the entire fire alarm system installation. Namely their call center operation. Rob wanted to know if this be accommodated, and if so how do they pursue this? I responded letting him know he would need to contact the appropriate inspector with this request.
Miscellaneous action  3/28/2013 DONE
An email from Rob Ahten w/ Protex stated that the approved job site plans have been lost and asked what to do. I let him know that I can leave a note to have someone take the plans to Idaho blueprint tomorrow during normal business hours. I asked him to please email me the contact name and phone number of the person that will be picking up and paying for the copies. In addition, once they have their copy, they need to call and/or email to make an appointment to have one of us wet-stamp/sign the copies. This appointment can’t be set up until they have been contacted by Idaho Blueprint letting them know the copies are ready.
Issue and Print Permit  3/20/2013 DONE
DetailsBarbara Stitt
Plan assigned to (Stephanie)2/25/2013 3/19/2013 DONE
DetailsStephanie L. Cobbley
Alarm Plan Check3/19/2013 3/19/2013 PASS
DetailsStephanie L. Cobbley
resubmittals approved with redlines and review comments
PLANS TAKEN FRONT DESK ALARM  3/19/2013 DONE
Approved plans taken to permit technician for processing.
Inspection Record Card- Fire3/19/2013 3/19/2013 DONE
DetailsBarbara Stitt
Permit Ready to Issue  3/19/2013 DONE
DetailsBarbara Stitt
Telephone call  3/19/2013 DONE
DetailsBarbara Stitt
Left message that permit is ready & fees due on 3-19-13 @ 11:45am///BAS
Plan resubmittals received  3/14/2013 DONE
DetailsTisha Gallop
received application and two copies of submittal documents and plans; routed to SLC
1st review completed  3/11/2013 FAIL
Alarm Plan Check3/11/2013 3/11/2013 FAIL
DetailsStephanie L. Cobbley
Plans denied - see review comments and redlines
Miscellaneous action  3/11/2013 DONE
Faxed review comments to applicant to let them know the plans have been denied and they can pick up the plans from the permit counter.
Plan resubmittals received  3/6/2013  
3-6-13 received 2 battery calcs and 4 copies of sheet PL121R sent to SLC
Application received  2/25/2013