INSP-Final Inspection | 4/4/2013 | 4/4/2013 | 4/4/2013 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final walkthrough, permit finaled.
|
INSP-Sprinkler Rough-in | 3/22/2013 | 3/22/2013 | 3/22/2013 | P | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler work at the grid ceilings.
|
Plan assigned to (Tim) | 2/28/2013 | | 2/28/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/28/2013 | | 2/28/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/28/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/28/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 2/28/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 2/28/2013 | | 2/28/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 2/27/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 27 2013 5:02PM
|