INSP-Final Inspection | 4/4/2013 | 4/5/2013 | 4/5/2013 | A | PASS |
Forrest France
|
|
|
Remainder of fire sprinkler work completed. Permit final approved.
|
INSP-Final Inspection | 4/2/2013 | 4/3/2013 | 4/3/2013 | A | PART |
Forrest France
|
|
|
Scope of work completed, however the plan modification could not be located on site. Also need to replace ceiling tile and provide access at one location as discussed.
|
CHANGE STATUS TO (REV) | | | 4/2/2013 | | |
|
|
|
PLAN MOD
|
Plan assigned to (Tim) | 4/2/2013 | | 4/2/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/2/2013 | | 4/2/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/2/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/2/2013 | | |
|
|
|
|
Issue and Print Permit | | | 4/2/2013 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 4/1/2013 | 4/1/2013 | 4/1/2013 | P | PART |
Forrest France
|
|
|
West conference room okay for cover.
|
INSP-Sprinkler Rough-in | 3/28/2013 | 3/29/2013 | 3/29/2013 | A | PART |
Forrest France
|
|
|
Overhead work at the new conference room okayed for ceiling cover. Coverage adjustments will also be necessary at an additional new room per the scope of remodel. Plan modification needed.
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2013 | 3/28/2013 | 3/28/2013 | P | PEND |
Forrest France
|
|
|
Scheduled 3/29
|
Plan assigned to (Tim) | 3/14/2013 | | 3/14/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/14/2013 | | 3/14/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/14/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/14/2013 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/14/2013 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/14/2013 | | 3/14/2013 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Application received | | | 3/12/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 12 2013 12:10PM
|