INSP-Final Inspection | 8/30/2013 | 8/30/2013 | 8/30/2013 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Troy Cobbley
|
|
|
Hydro test of the east system passed
|
INSP-Sprinkler Rough-in | 4/29/2013 | 4/30/2013 | 4/30/2013 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping in the LOC area is ok to cover.
|
INSP-Sprinkler Rough-in | 4/23/2013 | 4/23/2013 | 4/23/2013 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler protection is complete in Area "1A"
|
INSP-Sprinkler Rough-in | 4/17/2013 | 4/18/2013 | 4/18/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked "ok" in red where sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 4/10/2013 | 4/10/2013 | 4/10/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas in phase 1 where the sprinkler piping can be covered.
|
Sprinkler Plan Check | 3/29/2013 | | 3/29/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/29/2013 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/29/2013 | | 3/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 3/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 3/29/2013 | | 3/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 3/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (Tim) | 3/27/2013 | | 3/27/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/27/2013 | | 3/27/2013 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/27/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/27/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Application received | | | 3/22/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 22 2013 8:23AM
|