INSP-Final Inspection | 5/23/2013 | 5/23/2013 | 5/23/2013 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work completed.
|
INSP-Sprinkler Rough-in | 4/9/2013 | 4/9/2013 | 4/9/2013 | A | PART |
Forrest France
|
|
|
Okayed for cover, final pending ceiling tile and escutcheons. GC to verify existing system is current with an annual inspection.
|
INSP-Final Inspection | 3/26/2013 | 3/29/2013 | 3/29/2013 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler modifications are approved for cover.
|
Application received | | | 3/22/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 22 2013 9:42AM
|
Plan assigned to (Tim) | 3/22/2013 | | 3/22/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/22/2013 | | 3/22/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/22/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/22/2013 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/22/2013 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/22/2013 | | 3/22/2013 | | DONE |
Alexandra L. DeYoung
|
|
|
|