INSP-Final Inspection | 8/28/2013 | 8/29/2013 | 8/30/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 7/29/2013 | 7/29/2013 | 7/29/2013 | P | PASS |
Troy Cobbley
|
|
|
The piping in the room immediately across from the construction office is ok to cover.
|
INSP-Sprinkler Rough-in | 7/18/2013 | 7/19/2013 | 7/19/2013 | A | PASS |
Troy Cobbley
|
|
|
See areas marked "ok" where piping is ok to cover.
|
INSP-Sprinkler Rough-in | 7/8/2013 | 7/8/2013 | 7/8/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locatins marked "ok" where piping can be covered.
|
INSP-Sprinkler Rough-in | 6/25/2013 | 6/25/2013 | 6/26/2013 | P | PASS |
Troy Cobbley
|
|
|
The hydro test for the west wet system passed. Also see the city approved plans for additional areas where the sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 6/5/2013 | 6/6/2013 | 6/6/2013 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations marked ok where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 5/31/2013 | 5/31/2013 | 5/31/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations above hardlids where sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 5/10/2013 | 5/10/2013 | 5/10/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping can be covered.
|
Plan assigned to (Tim) | 4/9/2013 | | 4/9/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/9/2013 | | 4/9/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/9/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/9/2013 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/9/2013 | | 4/9/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 4/9/2013 | | DONE |
|
|
|
|
Application received | | | 4/8/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 8 2013 1:08PM
|