INSP-Final Inspection | 6/10/2013 | 6/11/2013 | 6/11/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Telephone call | | | 6/10/2013 | | DONE |
Lee G Meredith
|
|
|
I have reviewed the product data and discussed this communicator with the chief. We have determined that this product meets the minimal requirements for use as an IP type dialer. Approval is dependent upon installation of the product in full compliance with the manufacturers installation constraints to maintain UL listing requirements.
|
Telephone call | | | 6/10/2013 | | DONE |
Lee G Meredith
|
|
|
Informed Jason minnick that resubmital is not needed. Provide accurate update to as built drawings
|
INSP-Final Inspection | 5/17/2013 | 5/20/2013 | 5/20/2013 | A | FAIL |
Troy Cobbley
|
|
|
All devices tested ok but internet tech. is being used for the central station communication. The approved plans indicate two phone lines. Plan reviewer approval is needed for this. A plan modification may be required.
|
Permit Ready to Issue | | | 4/17/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 4/17/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 4/17/2013 | | 4/17/2013 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 4/16/2013 | | PASS |
|
|
|
|
Alarm Plan Check | 4/16/2013 | | 4/16/2013 | | PASS |
Stephanie L. Cobbley
|
|
|
Plans approved with field notes and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 4/16/2013 | | DONE |
|
|
|
updated in project dox
|
Plan assigned to (Stephanie) | 4/10/2013 | | 4/10/2013 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Application received | | | 4/9/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2013 1:40PM
|