Information based on query as of Friday, July 5, 2024.
Permit Information
Permit NumberFIR13-00178
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 1000 W MYRTLE ST
Project NameJUMP Parking Garage
Customer Number 
ePlanReviewYes
Description
This fire alarm permit is to provide a fire alarm system with voice evacuation for the parking garage only at this time. This permit scope of work includes a manual pull station, smoke detectors above the panels and for elevator recall functions, heat detectors, duct detectors for HVAC shutdown/monitoring, in-duct detectors for f/s damper shutdown/monitoring, full notification coverage for voice evacuation, sprinkler system monitoring, fire pump monitoring, heat tape monitoring, and elevator recall/shunt trip functions.
Associated building permit: BLD12-01330
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/7/201712/7/201712/7/2017APASS
DetailsJim Page
Final fire alarm inspection for scope of work passed/complete.
Miscellaneous action  11/29/2017 DONE
Shane emailed a copy of the state elevator inspector's approval report and asked if this was adequate or if a Boise City inspection is still required.
Miscellaneous action  11/27/2017 DONE
DetailsScott Arellano
Instructed staff to contact Fire Alarm permit applicants to call for final inspection.
Miscellaneous action  11/27/2017 DONE
I eamiled Dante asking him to corrdinate the outstanding east elevator recall and shunt final acceptance tests.
Miscellaneous action  11/27/2017 DONE
Shane Lesteberg of the local Simplex office replied to say he is working on this with Lea Electric. Indicated that the State Elevator Inspector had signed it off.
INSP-Final Inspection1/23/20171/23/20171/23/2017APART
DetailsJim Page
Partial final inspection for fire alarm system complete, permit can be finaled after inspection of east elevator recall/shunt is complete
INSP-Alarm Testing10/19/201510/19/201510/19/2015APART
DetailsThomas Walsh
Fire alarm interface with heat tracing panels that monitor heat trace of fire sprinkler piping exposed to cold temps. See FIR 13-00461 for details of heat trace inspection.
INSP-Alarm Testing7/12/20157/12/20157/12/2015PPART
DetailsThomas Walsh
test of fire sprinkler system for U/G parl'king garage, including four (4) dry pipe valves protecting the under ground parking garage and two (2) dry system suppling standpipes above the parking garage, including trip tests of the DP valves, low-air alarms, tampers and waterflows. All systems tested satisfactorily. Tom Walsh and Jim Page present for this inspection.
FIR-Aging Inspection6/30/20156/30/20156/30/2015 CANC
DetailsThomas Walsh
Wrong permit called in for this inspection. See FIR 13-00167 for hydrotest of U/G supply line (11th street connection).
INSP-Conference8/29/20148/29/20148/29/2014PCANC
DetailsForrest France
Call for access Phone #: 2089411846 >> Inspection requested via mobile web by Brian Anderson Inspection cancelled via mobile web on Friday, August 29, 2014.
Miscellaneous action  6/13/2013 DONE
DetailsLee G Meredith
Confirmed to Charlie that the garage and 5th floor would require voice evac and strobes throughout due to the mixed occupancy of parking, museum and amusement park.
Permit Ready to Issue  5/10/2013 DONE
Issue and Print Permit  5/10/2013 DONE
Inspection Record Card- Fire5/10/2013 5/10/2013 DONE
DetailsChristina Prado
1st review completed  5/9/2013 PASS
Alarm Plan Check5/9/2013 5/9/2013 PASS
DetailsStephanie L. Cobbley
plans approved with redlines and review comments.
PLANS TAKEN FRONT DESK ALARM  5/9/2013 DONE
updated in project dox
Plan assigned to (Stephanie)4/25/2013 4/25/2013 DONE
DetailsStephanie L. Cobbley
Application received  4/22/2013 DONE
Application submitted via PDS Online on Apr 22 2013 1:18PM