INSP-Final Inspection | 8/22/2013 | 8/22/2013 | 8/22/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Issue and Print Permit | | | 8/22/2013 | | DONE |
Rita DeYoung
|
|
|
this is a plan mod, customer needs inspection in area not affected by mod.
|
CHANGE STATUS TO (ISS) | | | 8/22/2013 | | DONE |
Tisha Gallop
|
|
|
status should have been changed to issued not ready...plan mod approved and paid for.
|
Sprinkler Plan Check | 8/21/2013 | | 8/21/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/21/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 8/21/2013 | | 8/21/2013 | | DONE |
Darla L Downs
|
|
|
|
(F) Reprint permit | | | 8/21/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/15/2013 | | 8/15/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/15/2013 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
INSP-Sprinkler Rough-in/Hydro | 8/7/2013 | 8/13/2013 | 8/13/2013 | A | PASS |
Troy Cobbley
|
|
|
It took two inspections but the overhead hydro passed.
|
INSP-Sprinkler Rough-in | 8/5/2013 | 8/6/2013 | 8/6/2013 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection verified that the seismic bracing had been installed on the gridded system in the Cafeteria. This included the branchlines and the far main.
|
INSP-Sprinkler Rough-in | 8/1/2013 | 8/5/2013 | 8/5/2013 | P | PART |
Troy Cobbley
|
|
|
Todays inspection was for the remaining first floor east corridor which has not been connected but is ok to cover. Also todays inspection was for the cafeteria which was already covered. Seismic bracing is missing on the branch lines and the 1 1/2" far main. Also the pipe routing has been modified for the branchlines and the new arm overs to the pendant heads. Plan modifications are required showing all of these changes and all of the other piping changes through-out the new system. Include the sprinkler heads model changes and revised hydraulic calculations.
|
INSP-Sprinkler Rough-in | 8/1/2013 | 8/5/2013 | 8/1/2013 | P | CANC |
Troy Cobbley
|
|
|
We need a 1st floor inspection. Please call Bruce 30 mins prior. Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
Miscellaneous action | | | 8/1/2013 | | DONE |
|
|
|
Switched Tyco extended coverage 11.2K sprinklers to Viking extended coverage 11.2K sprinklers
Coverage matched so the switch was OK
|
INSP-Sprinkler Rough-in/Hydro | 7/26/2013 | 7/29/2013 | 7/29/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the first floor areas where the sprinkler piping is ok to cover. Plan modifications may be needed showing the different sprinkler pendants installed and pipe routing changes. Contractor needs to have a conversation with the sprinkler plan reviewer to get a resolution.
|
INSP-Sprinkler Rough-in | 7/15/2013 | 7/16/2013 | 7/16/2013 | P | PART |
Troy Cobbley
|
|
|
RTC 2nd floor is mostly ok. Contractor needs to get with plan review but it appears a plan modification is needed since viking pendants were installed instead of tyco. Also the earthquake bracing has not been installed as shown on the plans. I'm ok with the second floor lay-in tile being installed in all locations except where I will need to view earth quake bracing.
|
INSP-Sprinkler Rough-in | 6/10/2013 | 6/11/2013 | 6/11/2013 | A | CANC |
Troy Cobbley
|
|
|
troy or joe @ ###-#### Phone #: ###-####
|
Sprinkler Plan Check | 5/15/2013 | | 5/15/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/15/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 5/15/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 5/15/2013 | | 5/15/2013 | | DONE |
Christina Prado
|
|
|
|
Miscellaneous action | | | 5/9/2013 | | DONE |
|
|
|
Call and asked for the correct drawing. The one that was supplied was named incorrectly.
|
1st review completed | | | 5/1/2013 | | FAIL |
|
|
|
|
Sprinkler Plan Check | 5/1/2013 | | 5/1/2013 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 5/1/2013 | | 5/1/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 4/24/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 24 2013 9:35AM
|