INSP-Final Inspection | 9/23/2013 | 9/24/2013 | 9/25/2013 | P | PASS |
Forrest France
|
|
|
Reinspection completed satisfactory. First floor dry system trip test passed after corrections made.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2013 | 9/12/2013 | 9/12/2013 | P | FAIL |
Forrest France
|
|
|
Time limitations per NFPA 13 for dry system water delivery were exceeded for the 1st floor system.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2013 | 9/12/2013 | 9/12/2013 | A | PART |
Forrest France
|
|
|
Completed hydrostatic testing of the new dry system piping at the 4th, 5th floors, and riser.
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2013 | 9/9/2013 | 9/12/2013 | P | PART |
Forrest France
|
|
|
Completed acceptable fire pump testing per NFPA 20 guidelines.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2013 | 9/11/2013 | 9/12/2013 | P | PART |
Forrest France
|
|
|
Completed satisfactory hydrostatic testing for the new dry system piping at the 1st, 2nd, and 3rd, floors. Also verified previous correction items are finished or underway.
|
INSP-Sprinkler Rough-in/Hydro | 9/9/2013 | 9/10/2013 | 9/11/2013 | P | NR |
Forrest France
|
|
|
Hydro for systems Phone #: ###-#### >> Inspection requested via web by John Venche
|
INSP-Sprinkler Rough-in/Hydro | 8/30/2013 | 9/5/2013 | 9/6/2013 | A | NR |
Forrest France
|
|
|
|
Sprinkler Plan Check | 6/11/2013 | | 6/11/2013 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
|
Miscellaneous action | | | 6/11/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Sprinkler Plan Check | 6/11/2013 | | 6/11/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/11/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 6/11/2013 | | 6/11/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 6/11/2013 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/11/2013 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/11/2013 | | 6/11/2013 | | DONE |
Darla L Downs
|
|
|
|
1st review completed | | | 6/7/2013 | | FAIL |
|
|
|
|
Sprinkler Plan Check | 6/7/2013 | | 6/7/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/7/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Plan assigned to (Tim) | 6/5/2013 | | 6/5/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/30/2013 | | DONE |
|
|
|
Application submitted via PDS Online on May 30 2013 9:21AM
|