INSP-Final Inspection | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | PASS |
Forrest France
|
|
|
Scope of work completed. Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 6/10/2013 | 6/11/2013 | 6/11/2013 | A | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler modifications at the grid ceiling areas as noted on approved plans.
|
Plan assigned to (Tim) | 6/3/2013 | | 6/6/2013 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 5/30/2013 | | 6/6/2013 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 5/30/2013 | | 6/6/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/6/2013 | | 6/6/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2013 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 6/6/2013 | | DONE |
Christina Prado
|
|
|
called Don to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 6/6/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 6/6/2013 | | 6/6/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 6/6/2013 | | DONE |
|
|
|
|
1st review completed | | | 6/3/2013 | | FAIL |
|
|
|
|
Sprinkler Plan Check | 6/3/2013 | | 6/3/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/3/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 6/3/2013 | | DONE |
Christina Prado
|
|
|
called Don to advise resubmittals are needed
|
Plan resubmittals received | | | 6/3/2013 | | |
|
|
|
Received 1 Fire Sprinkler Quick Permit re-submittal taken to Tim F.
|
Application received | | | 5/30/2013 | | |
|
|
|
|