INSP-Final Inspection | 7/30/2013 | 7/30/2013 | 7/31/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final walkthrough.
|
INSP-Sprinkler Rough-in | 6/24/2013 | 6/25/2013 | 6/25/2013 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at room 104B okay to cover.
|
Issue and Print Permit | | | 6/10/2013 | | DONE |
Barbara Stitt
|
|
|
|
Sprinkler Plan Check | 6/7/2013 | | 6/7/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/7/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2013 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Scott) | | | 5/31/2013 | | DONE |
Bill Alexander
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 5/31/2013 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|