Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 7/23/2013 | 7/23/2013 | 7/23/2013 | P | PASS |
Forrest France
|
|
|
Inspection passed. Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 6/19/2013 | 6/20/2013 | 6/20/2013 | A | PART |
Forrest France
|
|
|
Okay to cover remainder of overhead fire sprinkler work.
|
INSP-Sprinkler Rough-in | 6/18/2013 | 6/19/2013 | 6/19/2013 | A | PART |
Forrest France
|
|
|
Overhead work as marked on approved plans with the exception of one pendent yet to be relocated okayed for cover.
|
Issue and Print Permit | | | 6/17/2013 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 6/5/2013 | | 6/12/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/12/2013 | | 6/12/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/12/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 6/12/2013 | | 6/12/2013 | | DONE |
Darla L Downs
|
|
|
|
Telephone call | | | 6/12/2013 | | |
|
|
|
6-12-13 Called Don -Curtis Fire permit ready and fee given ///dld
|
Plan resubmittals received | | | 6/11/2013 | | DONE |
Christina Prado
|
|
|
Received three sets of revised applications, checklists, calcs and plans marked A0.0: routed to Tim for review
|
1st review completed | | | 6/10/2013 | | FAIL |
|
|
|
|
Sprinkler Plan Check | 6/10/2013 | | 6/10/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/10/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 6/10/2013 | | |
|
|
|
6-10-13 called Don-Curtis fire sprinkler permit ready for pick up ///dld
|
Application received | | | 6/5/2013 | | |
|
|
|
|