Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR13-00248
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 300 S CAPITOL BLVD
Project NameRetail 1 Capitol & Front
Customer NumberUDG ONLY
ePlanReviewYes
Description
The fire sprinkler scope of work consists of installing 152’ of 6" C-900 underground piping with associated fittings and thrust blocks.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/23/201310/24/201310/24/2013APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection10/21/201310/22/201310/23/2013PNR
DetailsForrest France
Pending items for project related OH FIR13-00348 including forward flow, access to the FDC, outside bell is not functional, need verification of dry system capacity as trip testing time results over 60 sec., DP heads are not yet installed at the outside canopies.
INSP-Supply line flush9/26/20139/27/20139/27/2013APASS
DetailsTroy Cobbley
Underground flush passed
INSP-Supply line flush9/4/20139/5/20139/6/2013PDEFR
DetailsForrest France
Water supply not yet available to complete flushing per contractor.
Inspection8/27/20138/27/20138/27/2013PPASS
DetailsTim Frost
Underground Hydro Passed
INSP-Sprinkler Rough-in8/2/20138/5/20138/5/2013APASS
DetailsTroy Cobbley
Underground ok to cover as marked on the plan.
INSP-Sprinkler Rough-in7/18/20137/19/20137/19/2013PCANC
DetailsTroy Cobbley
Wrong permit number number called in. The two correct permit numbers are called in for mandya to make the entries. They are FIR13-00249 and 250. Each of these underground supply lines is ok for cover as marked on the city approved plans.
Sprinkler Plan Check6/19/2013 6/19/2013 PASS
DetailsTim Frost
with Conditions
PLANS/APPL TAKEN TO FRONT DESK  6/19/2013 DONE
DetailsTim Frost
Permit Ready to Issue  6/19/2013 DONE
DetailsChristina Prado
Issue and Print Permit  6/19/2013 DONE
DetailsChristina Prado
Inspection Record Card- Fire6/19/2013 6/19/2013 DONE
DetailsChristina Prado
Plan assigned to (Tim)6/10/2013 6/10/2013 DONE
DetailsTim Frost
Sprinkler Plan Check6/10/2013 6/10/2013 FAIL
DetailsTim Frost
1st review completed  6/10/2013 FAIL
Application received  6/6/2013 DONE