INSP-Final Inspection | 10/23/2013 | 10/24/2013 | 10/24/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/21/2013 | 10/22/2013 | 10/23/2013 | P | NR |
Forrest France
|
|
|
Pending items for project related OH FIR13-00348 including forward flow, access to the FDC, outside bell is not functional, need verification of dry system capacity as trip testing time results over 60 sec., DP heads are not yet installed at the outside canopies.
|
INSP-Supply line flush | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Supply line flush | 9/4/2013 | 9/5/2013 | 9/6/2013 | P | DEFR |
Forrest France
|
|
|
Water supply not yet available to complete flushing per contractor.
|
Inspection | 8/27/2013 | 8/27/2013 | 8/27/2013 | P | PASS |
Tim Frost
|
|
|
Underground Hydro Passed
|
INSP-Sprinkler Rough-in | 8/2/2013 | 8/5/2013 | 8/5/2013 | A | PASS |
Troy Cobbley
|
|
|
Underground ok to cover as marked on the plan.
|
INSP-Sprinkler Rough-in | 7/18/2013 | 7/19/2013 | 7/19/2013 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number number called in. The two correct permit numbers are called in for mandya to make the entries. They are FIR13-00249 and 250. Each of these underground supply lines is ok for cover as marked on the city approved plans.
|
Sprinkler Plan Check | 6/19/2013 | | 6/19/2013 | | PASS |
Tim Frost
|
|
|
with Conditions
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/19/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 6/19/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 6/19/2013 | | 6/19/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 6/10/2013 | | 6/10/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/10/2013 | | 6/10/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/10/2013 | | FAIL |
|
|
|
|
Application received | | | 6/6/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 6 2013 10:20AM
|