INSP-Final Inspection | 8/21/2013 | 8/22/2013 | 8/22/2013 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final walkthrough.
|
INSP-Sprinkler Rough-in | 7/8/2013 | 7/9/2013 | 7/9/2013 | A | PART |
Forrest France
|
|
|
Okay to cover scope of work at the 3rd floor remodel area including field changes.
|
Permit Ready to Issue | | | 6/13/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 6/13/2013 | | 6/13/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 6/13/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/12/2013 | | 6/12/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/12/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/11/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 11 2013 10:40AM
|