INSP-Final Inspection | 9/18/2013 | 9/19/2013 | 9/19/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/3/2013 | 9/3/2013 | 9/5/2013 | P | PART |
Forrest France
|
|
|
Inspection intended for kitchen freezer only.
|
INSP-Sprinkler Rough-in | 9/3/2013 | 9/3/2013 | 9/5/2013 | P | PART |
Forrest France
|
|
|
Inspection for new dry pendent coverage at the kitchen freezer completed and passed.
|
INSP-Final Inspection | 7/18/2013 | 7/22/2013 | 7/22/2013 | A | PART |
Troy Cobbley
|
|
|
Dish washing area as marked on the city approved plans is ok for cover.
|
INSP-Final Inspection | 7/12/2013 | 7/15/2013 | 7/15/2013 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was just a final for the "dry storage" area. Sprinklers are complete in this area but other areas are still under construction.
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2013 | 6/27/2013 | 6/27/2013 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the two locations where sprinkler piping can be covered which includes dry storage and a short corridor.
|
Sprinkler Plan Check | 6/18/2013 | | 6/18/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/18/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/18/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Sprinkler Plan Check | 6/18/2013 | | 6/18/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/18/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue and Print Permit | | | 6/18/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Fire | 6/18/2013 | | 6/18/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Tim) | 6/17/2013 | | 6/17/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/13/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 13 2013 10:59AM
|