INSP-Final Inspection | 9/20/2013 | 9/20/2013 | 9/20/2013 | P | PASS |
Forrest France
|
|
|
Fire alarm work passed after corrections made on site. Permit finaled.
|
INSP-Final Inspection | 9/17/2013 | 9/18/2013 | 9/19/2013 | P | FAIL |
Forrest France
|
|
|
Noted missing SD at the employee lunchroom E107. Overspaced notification adjusted while on site.
|
INSP-Final Inspection | 9/17/2013 | 9/17/2013 | 9/18/2013 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow after 4pm with Forrest
|
INSP-Final Inspection | 7/18/2013 | 7/19/2013 | 7/19/2013 | A | PART |
Troy Cobbley
|
|
|
The two smoke detectors in the Dry Storage tested ok. The city approved plans only show one smoke detector. As-builts will need to be provided.
|
Permit Ready to Issue | | | 7/9/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 7/9/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 7/9/2013 | | 7/9/2013 | | DONE |
Christina Prado
|
|
|
|
Miscellaneous action | | | 7/3/2013 | | |
|
|
|
|
Miscellaneous action | | | 7/3/2013 | | DONE |
|
|
|
Projectdox locked up so case would not continue processing. Jim Tooms made repairs and projectdox process were completed.
|
1st review completed | | | 6/28/2013 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/28/2013 | | PASS |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 6/28/2013 | | DONE |
Lee G Meredith
|
|
|
Emailed review comments to client
|
Plan assigned to (Lee) | 6/26/2013 | | 6/26/2013 | | DONE |
Lee G Meredith
|
|
|
|
Alarm Plan Check | 6/26/2013 | | 6/26/2013 | | PASS |
Lee G Meredith
|
|
|
|
Application received | | | 6/25/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 25 2013 9:54AM
|