INSP-Final Inspection | 9/17/2013 | 9/17/2013 | 9/17/2013 | P | PASS |
Forrest France
|
|
|
Final walkthrough of the permit work passed inspection. Fire sprinkler finaled.
|
INSP-Sprinkler Rough-in | 9/13/2013 | 9/13/2013 | 9/16/2013 | P | PART |
Forrest France
|
|
|
Okay to cover fire sprinkler work at the remainder of grid ceilings in the remodel area (phase 2).
|
INSP-Sprinkler Rough-in | 8/8/2013 | 8/9/2013 | 8/9/2013 | A | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler work at project "phase one" as annotated and initialed on stamped plans.
|
Issue and Print Permit | | | 7/17/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 7/2/2013 | | 7/5/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/5/2013 | | 7/5/2013 | | PASS |
Scott Arellano
|
|
|
No comments attached to plans.
|
1st review completed | | | 7/5/2013 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/5/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 7/5/2013 | | 7/5/2013 | | DONE |
Darla L Downs
|
|
|
|
Telephone call | | | 7/5/2013 | | |
|
|
|
7-5-13 called Don- Curtis firesprinkler permit ready and fee given ///dld
|
Application received | | | 7/2/2013 | | |
|
|
|
|