Miscellaneous action | | | 3/6/2014 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 11/18/2013 | 11/19/2013 | 11/19/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2013 | 11/19/2013 | 11/19/2013 | A | PASS |
Troy Cobbley
|
|
|
cover & hydro // Don Phone #: ###-####
|
INSP-Supply line flush | 11/7/2013 | 11/7/2013 | 11/7/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2013 | 8/5/2013 | 8/5/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in | 7/23/2013 | 7/24/2013 | 7/24/2013 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover.
|
Issue and Print Permit | | | 7/22/2013 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 7/2/2013 | | 7/18/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/18/2013 | | 7/18/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/18/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 7/18/2013 | | 7/18/2013 | | DONE |
Darla L Downs
|
|
|
|
Telephone call | | | 7/18/2013 | | |
|
|
|
7-18-13 called Don - Curtis Fire permit ready and fee given ///dld
|
Plan resubmittals received | | | 7/16/2013 | | |
|
|
|
|
1st review completed | | | 7/12/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/12/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Sprinkler Plan Check | 7/12/2013 | | 7/12/2013 | | FAIL |
Tim Frost
|
|
|
|
Telephone call | | | 7/12/2013 | | DONE |
Tisha Gallop
|
|
|
called Don and told him denied plans at front desk.
|
Application received | | | 7/2/2013 | | |
|
|
|
|