Permit Information
Permit NumberFIR13-00299
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 5500 S FEDERAL WAY
Project NameOrePac Paint Booth Room
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of three new spray booths, one mixing/storage room, one halogen oven tunnel and 1 casing sprayer in a new enclosed room. The overhead sprinkler system is existing. New drops from the existing mains are being provided to the new paint booths.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/15/20138/16/20138/16/2013APASS
DetailsForrest France
Fire sprinkler permit work passed final inspection and walkthrough.
INSP-Final Inspection8/15/20138/15/20138/15/2013APART
DetailsForrest France
Rough-in completed, inspection passed.
INSP-Sprinkler Rough-in/Hydro8/8/20138/9/20138/9/2013PPART
DetailsForrest France
OH hydrostatic testing for the new system additions completed satisfactory. Also completed rough-in inspection.
Sprinkler Plan Check8/8/2013 8/8/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  8/8/2013 DONE
DetailsTim Frost
(F) Reprint permit  8/8/2013 DONE
Inspection Record Card- Fire8/8/2013 8/8/2013 DONE
DetailsDarla L Downs
CHANGE STATUS TO (ISS)  8/8/2013  
Telephone call  8/8/2013 DONE
Left message for Bret. I need to know if the new raise platform is of combustible construction. Told him the project was on hold until I heard from him.
INSP-Conference8/5/20138/6/20138/6/2013PDONE
DetailsForrest France
On site conference regarding review note item #7, and conditions per NFPA 13 24.2.1.6.
INSP-Sprinkler Rough-in/Hydro8/5/20138/6/20138/6/2013PCANC
DetailsForrest France
cesar Phone #: ###-####
Permit Ready to Issue  7/22/2013 DONE
DetailsChristina Prado
Issue and Print Permit  7/22/2013 DONE
DetailsChristina Prado
Inspection Record Card- Fire7/22/2013 7/22/2013 DONE
DetailsChristina Prado
Sprinkler Plan Check7/17/2013 7/17/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  7/17/2013 DONE
DetailsTim Frost
Sprinkler Plan Check7/12/2013 7/12/2013 FAIL
DetailsTim Frost
1st review completed  7/12/2013 PASS
DetailsTim Frost
Plan assigned to (Tim)7/10/2013 7/10/2013 DONE
DetailsTim Frost
Application received  7/8/2013 DONE
Application submitted via PDS Online on Jul 8 2013 2:11PM. Workflow inititiated by Plan Review.