Miscellaneous action | | | 3/6/2014 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 10/8/2013 | 10/8/2013 | 10/8/2013 | P | PASS |
Forrest France
|
|
|
C/N items field verified for completion. CPVC piping at the basement level now meets mfg. guidelines for exposed installation. Fire sprinkler permit finaled.
|
Sprinkler Plan Check | 10/7/2013 | | 10/7/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/7/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/7/2013 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/7/2013 | | 10/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 10/7/2013 | | DONE |
Tisha Gallop
|
|
|
called Don at Curtis Fire and told him plan mod is ready and no fee due.
|
CHANGE STATUS TO (ISS) | | | 10/7/2013 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 10/4/2013 | | 10/7/2013 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 10/4/2013 | | |
|
|
|
Received 3 copies of letter from Don Curtis to Tim Frost dated 10-3-13, 3 copies of addendum #1, 3 copies of sheet FP-01
|
INSP-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 | A | PART |
Forrest France
|
|
|
Completed walkthrough- Need to install missing heads at the garage/riser areas, secure control valves at the riser, include finish pack with spare heads, calc sticker, etc. Flow switch tested okay, one missing escutcheon installed while on site. Need to provide thermal barrier or meet conditions for exposed CPVC pipe at the ground level unfinished bedroom, family room, WIC and under stair storage areas.
|
INSP-Sprinkler Rough-in | 8/5/2013 | 8/6/2013 | 8/6/2013 | A | PART |
Forrest France
|
|
|
Tenting inspection completed satisfactory- okay to cover overhead rough-in.
|
INSP-Sprinkler Rough-in | 8/2/2013 | 8/2/2013 | 8/2/2013 | P | PART |
Troy Cobbley
|
|
|
rough-in passed. As-builts are needed prior to a final sign off that show theactual pipe routing. Piping can not be covered until a tenting inspection has been performed. Also the underground supply is a combined service with the domestic which, as noted on the city approved plans/notes, is not United Water approved.
|
Issue and Print Permit | | | 7/30/2013 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 7/11/2013 | | 7/29/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/29/2013 | | 7/29/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/29/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 7/29/2013 | | 7/29/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 7/29/2013 | | DONE |
Christina Prado
|
|
|
called Curtis to advise permit it ready and gave fees due
|
Miscellaneous action | | | 7/23/2013 | | DONE |
|
|
|
Emailed Don Curtis Fire Sprinkler Services, Inc. and told him specifically that a combined service went against United Water policy; a separate tap just for the sprinkler system was requied
|
Plan resubmittals received | | | 7/18/2013 | | DONE |
Tisha Gallop
|
|
|
received three copies of application, submittal documents and plans; routed to fire
|
Sprinkler Plan Check | 7/16/2013 | | 7/16/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 7/16/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/16/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Application received | | | 7/11/2013 | | |
|
|
|
|