INSP-Final Inspection | 10/25/2013 | 10/25/2013 | 10/25/2013 | P | PASS |
Craig D. Hanson
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2013 | 8/13/2013 | 8/13/2013 | P | PASS |
Troy Cobbley
|
|
|
Under ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 7/23/2013 | 7/24/2013 | 7/24/2013 | P | PASS |
Troy Cobbley
|
|
|
Supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 7/23/2013 | 7/24/2013 | 7/23/2013 | A | CANC |
Troy Cobbley
|
|
|
Please schedule for late morning if possible. Contact Mike Elston at ###-#### 30 minutes prior to inspection Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
Sprinkler Plan Check | 7/23/2013 | | 7/23/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2013 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 7/23/2013 | | 7/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 7/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Miscellaneous action | | | 7/22/2013 | | DONE |
|
|
|
Gave Trent the OK for the underground. The FDC and bell are wrong and will be resubmitted in the overhead drawings.
|
Plan assigned to (Tim) | 7/18/2013 | | 7/18/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/18/2013 | | 7/18/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 7/18/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/18/2013 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Application received | | | 7/17/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 17 2013 10:13AM
|