INSP-Final Inspection | 10/10/2013 | 10/11/2013 | 10/11/2013 | A | PASS |
Craig D. Hanson
|
|
|
|
Miscellaneous action | | | 10/8/2013 | | DONE |
|
|
|
Sent email to Tom Easton.
Happen to cruise by Trader Joes today. You have a problem with the FDC and the flow switch and will need to be adjusted. They are both blocked by metal facade they have put on the outside of the building
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2013 | 10/4/2013 | 10/4/2013 | A | PART |
Forrest France
|
|
|
Concluded satisfactory 24 hr. air test within allowable pressure loss per NFPA13.
|
INSP-Sprinkler Rough-in | 10/1/2013 | 10/2/2013 | 10/3/2013 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic testing completed okay
|
INSP-Sprinkler Rough-in | 10/2/2013 | 10/3/2013 | 10/3/2013 | A | PART |
Forrest France
|
|
|
Begin 24 hr. air test of the overhead dry system at 11:15AM @41psig.
|
Override - Parcel Holds | 10/2/2013 | 1/1/1900 | 10/2/2013 | | |
|
|
|
24hr air test
|
Override - Parcel Holds | 10/1/2013 | 1/1/1900 | 10/1/2013 | | |
|
|
|
fir
|
INSP-Sprinkler Rough-in | 9/25/2013 | 9/26/2013 | 9/26/2013 | A | PASS |
Craig D. Hanson
|
|
|
Rough in pass-still need to look at riser and bracing for riser before cover.
|
Sprinkler Plan Check | 9/25/2013 | | 9/25/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/25/2013 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/25/2013 | | DONE |
Christina Prado
|
|
|
|
INSP-Supply line flush | 9/4/2013 | 9/5/2013 | 9/6/2013 | P | DEFR |
Forrest France
|
|
|
Water supply not yet available to complete flushing per contractor.
|
Permit Ready to Issue | | | 8/9/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 8/9/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 8/9/2013 | | 8/9/2013 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 8/8/2013 | | 8/8/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2013 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 7/30/2013 | | 7/30/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/30/2013 | | 7/30/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 7/30/2013 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 7/30/2013 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 7/24/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 24 2013 4:19PM
|
INSP-Supply line flush | 9/5/2013 | 9/6/2013 | | P | |
Forrest France
|
|
|
Nate is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|