Permit Information
Permit NumberFIR13-00348
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 300 S CAPITOL BLVD
Project NameRetail 1 Capitol & Front
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of a 2 double tree dry system with telescoping branch piping, 4” mains,6” riser and 6” backflow preventer.

The underground piping is under permit FIR13-00248
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/10/201310/11/201310/11/2013APASS
DetailsCraig D. Hanson
Miscellaneous action  10/8/2013 DONE
Sent email to Tom Easton.

Happen to cruise by Trader Joes today. You have a problem with the FDC and the flow switch and will need to be adjusted. They are both blocked by metal facade they have put on the outside of the building
INSP-Sprinkler Rough-in/Hydro10/3/201310/4/201310/4/2013APART
DetailsForrest France
Concluded satisfactory 24 hr. air test within allowable pressure loss per NFPA13.
INSP-Sprinkler Rough-in10/1/201310/2/201310/3/2013PPART
DetailsForrest France
Overhead hydrostatic testing completed okay
INSP-Sprinkler Rough-in10/2/201310/3/201310/3/2013APART
DetailsForrest France
Begin 24 hr. air test of the overhead dry system at 11:15AM @41psig.
Override - Parcel Holds10/2/20131/1/190010/2/2013  
24hr air test
Override - Parcel Holds10/1/20131/1/190010/1/2013  
fir
INSP-Sprinkler Rough-in9/25/20139/26/20139/26/2013APASS
DetailsCraig D. Hanson
Rough in pass-still need to look at riser and bracing for riser before cover.
Sprinkler Plan Check9/25/2013 9/25/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  9/25/2013 DONE
DetailsTim Frost
Permit Ready to Issue  9/25/2013 DONE
DetailsChristina Prado
CHANGE STATUS TO (ISS)  9/25/2013 DONE
DetailsChristina Prado
INSP-Supply line flush9/4/20139/5/20139/6/2013PDEFR
DetailsForrest France
Water supply not yet available to complete flushing per contractor.
Permit Ready to Issue  8/9/2013 DONE
DetailsChristina Prado
Issue and Print Permit  8/9/2013 DONE
DetailsChristina Prado
Inspection Record Card- Fire8/9/2013 8/9/2013 DONE
DetailsChristina Prado
Sprinkler Plan Check8/8/2013 8/8/2013 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  8/8/2013 DONE
DetailsTim Frost
Plan assigned to (Tim)7/30/2013 7/30/2013 DONE
DetailsTim Frost
Sprinkler Plan Check7/30/2013 7/30/2013 FAIL
DetailsTim Frost
1st review completed  7/30/2013 FAIL
DetailsTim Frost
Miscellaneous action  7/30/2013 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  7/24/2013 DONE
Application submitted via PDS Online on Jul 24 2013 4:19PM
INSP-Supply line flush9/5/20139/6/2013 P 
DetailsForrest France
Nate is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus