INSP-Final Inspection | 10/10/2013 | 10/11/2013 | 10/11/2013 | A | PASS |
Craig D. Hanson
|
|
|
trip test and pitot test pass
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2013 | 10/4/2013 | 10/4/2013 | A | PART |
Forrest France
|
|
|
24hr. air test of the overhead dry system completed satisfactory.
|
INSP-Sprinkler Rough-in | 10/2/2013 | 10/3/2013 | 10/3/2013 | A | PART |
Forrest France
|
|
|
Begin 24 hr. air test of the new dry system at 10:30AM @42psig.
|
Override - Parcel Holds | 10/2/2013 | 1/1/1900 | 10/2/2013 | | |
|
|
|
24hr air test
|
INSP-Sprinkler Rough-in | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | PASS |
Troy Cobbley
|
|
|
Rough-in inspection for the outside canopy passed
|
INSP-Sprinkler Rough-in | 9/25/2013 | 9/26/2013 | 9/26/2013 | A | PART |
Forrest France
|
|
|
Need Rough-in inspection on fire sprinkler system. Please contact Nate with questions ###-#### Phone #: ###-#### >> Inspection requested via web by Stan Beus * NOTE- site inspection by C. Hanson w/ FIR13-00348*
|
Permit Ready to Issue | | | 8/15/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 8/15/2013 | | 8/15/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 8/15/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/14/2013 | | 8/14/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/14/2013 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 7/30/2013 | | 7/30/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/30/2013 | | 7/30/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 7/30/2013 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 7/24/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 24 2013 4:25PM
|