INSP-Final Inspection | 11/18/2013 | 11/18/2013 | 11/18/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit work okayed for final.
|
INSP-Final Inspection | 11/14/2013 | 11/15/2013 | 11/15/2013 | A | PART |
Forrest France
|
|
|
Fire sprinkler work at the new warehouse area passed overhead inspection. Discussed light fixture locations with respect to sprinkler head coverage with electrical contractor. Final pending lacking coverage above the hall ceiling adjacent to the secure storage room where the deck sprinklers will be obstructed.
|
Fees Due Hold | 10/17/2013 | | 10/17/2013 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Fire | 10/17/2013 | | 10/17/2013 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 10/17/2013 | | DONE |
Barbara Stitt
|
|
|
|
Issue and Print Permit | | | 10/16/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/15/2013 | | 10/15/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2013 | | DONE |
Tim Frost
|
|
|
|
INSP-Sprinkler Rough-in | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | PART |
Forrest France
|
|
|
Remainder of overhead work okay for ceiling cover.
|
INSP-Sprinkler Rough-in | 8/22/2013 | 8/23/2013 | 8/23/2013 | A | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler work at reception 101, and restrooms 102/103.
|
Plan assigned to (Tim) | 7/31/2013 | | 7/31/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/31/2013 | | 7/31/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/31/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 7/31/2013 | | |
|
|
|
|
Issue and Print Permit | | | 7/31/2013 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/31/2013 | | 7/31/2013 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | | 7/25/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 25 2013 10:51AM
|