INSP-Final Inspection | 8/21/2013 | 8/22/2013 | 8/22/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 8/6/2013 | 8/6/2013 | 8/6/2013 | P | PART |
Forrest France
|
|
|
Fire sprinkler work at the drop ceilings approved for cover.
|
Plan assigned to (Tim) | 8/5/2013 | | 8/5/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/5/2013 | | 8/5/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/5/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/5/2013 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 8/5/2013 | | 8/5/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 8/5/2013 | | DONE |
|
|
|
|
Application received | | | 8/2/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 2 2013 2:01PM
|