INSP-Final Inspection | 9/30/2013 | 10/1/2013 | 10/1/2013 | P | PASS |
Forrest France
|
|
|
Previous correction items finished. Reinspection passed. Fire alarm permit finaled.
|
INSP-Final Inspection | 9/27/2013 | 9/27/2013 | 9/27/2013 | P | FAIL |
Troy Cobbley
|
|
|
Need as-builts showing the changes and the a/v's need to be sync's. Also the building address has changed. Robert is going to follow up on the monitoring address change.
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2013 | 9/27/2013 | 9/27/2013 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Robert Gobler Inspection cancelled from web by: Robert Gobler
|
Issue and Print Permit | | | 8/13/2013 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 8/8/2013 | | 8/9/2013 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 8/9/2013 | | PASS |
Lee G Meredith
|
|
|
|
Alarm Plan Check | 8/9/2013 | | 8/9/2013 | | PASS |
Lee G Meredith
|
|
|
Plans approved subject to redline notes on drawing, submittal data and NAC calculation.
|
PLANS TAKEN FRONT DESK ALARM | | | 8/9/2013 | | DONE |
Lee G Meredith
|
|
|
Plans taken to front desk for processing.
|
Telephone call | | | 8/9/2013 | | DONE |
Christina Prado
|
|
|
called Robert to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 8/9/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 8/9/2013 | | 8/9/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 8/8/2013 | | |
|
|
|
|