INSP-Final Inspection | 12/9/2013 | 12/10/2013 | 12/10/2013 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection and walkthrough.
|
INSP-Final Inspection | 12/6/2013 | 12/9/2013 | 12/9/2013 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm sytem is not ready for testing.Tamper switches are not connected and the system is in "trouble"
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2013 | 12/6/2013 | 12/6/2013 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic testing for the first and second floors completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2013 | 12/5/2013 | 12/5/2013 | P | FAIL |
Troy Cobbley
|
|
|
The hydro test failed for a second time. There is visible leakage at the left hand riser flow switch. Not sure where the leak is on the right hand riser.
|
INSP-Sprinkler Rough-in | 12/4/2013 | 12/5/2013 | 12/5/2013 | A | FAIL |
Troy Cobbley
|
|
|
Hydro test failed due to visible drop in pressure at the guages.
|
INSP-Sprinkler Rough-in | 9/6/2013 | 9/9/2013 | 9/9/2013 | A | PART |
Forrest France
|
|
|
Tenting inspection completed. Rough-in okay to cover.
|
INSP-Sprinkler Rough-in | 9/5/2013 | 9/5/2013 | 9/6/2013 | P | PART |
Forrest France
|
|
|
Piping to added heads at the fireplace inserts needs nailer plates and freeze protection.
|
INSP-Sprinkler Rough-in | 9/3/2013 | 9/3/2013 | 9/5/2013 | P | PART |
Forrest France
|
|
|
Overhead rough-in completed with the exception of upright coverage at two fireplace enclosures as shown per stamped plans. Tenting and cold cavity protection not yet installed.
|
Permit Ready to Issue | | | 8/27/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 8/27/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 8/27/2013 | | 8/27/2013 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 8/23/2013 | | 8/23/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/21/2013 | | 8/21/2013 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/21/2013 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 8/20/2013 | | 8/20/2013 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/14/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 14 2013 2:39PM
|