INSP-Final Inspection | 11/20/2013 | 11/20/2013 | 11/20/2013 | P | PASS |
Forrest France
|
|
|
Final walkthrough passed. Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in | 9/11/2013 | 9/11/2013 | 9/12/2013 | P | PART |
Forrest France
|
|
|
Overhead work okayed to cover under condition record drawings are provided reflecting field changes in pipe routing.
|
INSP-Sprinkler Rough-in | 8/22/2013 | 8/23/2013 | 8/23/2013 | A | PART |
Forrest France
|
|
|
New head at the master bath and one relocated head at the master bedroom as marked on approved plans okayed to cover- Discussed cold cavity protection requirements.
|
Plan assigned to (Tim) | 8/22/2013 | | 8/22/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/22/2013 | | 8/22/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/22/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/22/2013 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 8/22/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 8/22/2013 | | 8/22/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 8/20/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 20 2013 6:00PM
|